RESTITUTION OF DEVELOPMENT GAINS ACT
6249 · 2006-01-01
RESTITUTION OF DEVELOPMENT GAINS ACT
Act No. 7709, Dec. 7, 2005
Act No. 4175, Dec. 30, 1989
Amended by Act No. 4434, Dec. 14, 1991
Act No. 4563, Jun. 11, 1993
Act No. 5116, Dec. 29, 1995
Act No. 5108, Dec. 29, 1995
Act No. 5285, Jan. 13, 1997
Act No. 5409, Aug. 30, 1997
Act No. 5572, Sep. 19, 1998
Act No. 5586, Dec. 28, 1998
Act No. 6202, Jan. 21, 2000
Act No. 6558, Dec. 31, 2001
Act No. 6656, Feb. 4, 2002
Act No. 6655, Feb. 4, 2002
Act No. 6832, Dec. 26, 2002
Act No. 6841, Dec. 30, 2002
Act No. 6916, May 29, 2003
Act No. 7061, Jan. 16, 2004
Act No. 7335, Jan. 14, 2005
Act No. 7709, Dec. 7, 2005
CHAPTER I GENERAL PROVISIONS
법령보기 화면
Article 1 (Purpose)
The purpose of this Act is to prevent the speculation on land, promote the effective utilization of land and contribute to the sound development of the national economy by restituting the development gains accruing from land and distributing them properly.
법령보기 화면
Article 2 (Definitions)
The definitions of terms as used in this Act shall be as follows:
<Amended by Act No. 4563, Jun. 11, 1993; Act No. 5285. Jan. 13, 1997; Act No. 6202, Jan. 21, 2000; Act No. 6655, Feb. 4, 2002>
1.
"Development gains" means increases in land prices reverting to a person who executes the development works (hereinafter referred to as the "project operator") or the landowner in excess of increases in normal land prices due to the execution of development works, change of land-use plan or other social and economic factors;
2.
"Development works" means the works referred to in
Article 5
such as housing site development works and industrial complex preparation works which are executed with authorization, permission, license, etc. (including report and hereinafter referred to as the "authorization, etc.") from the State or the local government;
3.
"Increases in normal land prices" means the amount calculated in accordance with the standards as determined by the Presidential Decree in consideration of the interest rates of term deposits in financial institutions and the average rate of fluctuation in land prices investigated by the Minister of Construction and Transportation pursuant to
Article 125 of the National Land Planning and Utilization Act
(referring to the average rate of fluctuation in land prices of the relevant
Si
/
Gun
or autonomous
Gu
in which the area subject to the development work concerned is located); and
4.
"Development charges" means the amount imposed on and collected by the State from the development gains under this Act.
법령보기 화면
Article 3 (Restitution of Development Gains)
(1)
The State shall collect the development gains arising from the region in which the works subject to imposition of development charges referred to in
Article 5
are executed as development charges under the conditions as determined by this Act.
<Amended by Act No. 4563, Jun. 11, 1993>
(2)
Deleted.
<by Act No. 5586, Dec. 28, 1998>
법령보기 화면
Article 4 (Distribution of Impositions)
(1)
The amount equivalent to 50/100 of the development charges collected pursuant to
Article 3
(1) shall revert to the local government to which the land on which the development gains occur belongs, and the rest of the development charges shall revert to the special accounts for balanced national development (hereinafter referred to as "special accounts") which are otherwise determined by Act.
<Amended by Act No. 7061, Jan. 16, 2005>
(2)
Deleted.
<by Act No. 5586, Dec. 28, 1998>
(3)
Matters necessary for the reversion, grant or transfer procedures, etc. referred to in paragraph (1) shall be determined by the Presidential Decree.
<Amended by Act No. 5586, Dec. 28, 1998>
CHAPTER II DEVELOPMENT CHARGES
Section 1 Common Provisions
법령보기 화면
Article 5 (Projects of Object)
(1)
The development works subject to imposition of the development charges shall be the projects, etc. falling under any of the following subparagraphs:
<Amended by Act No. 4434, Dec. 14, 1991; Act No. 4563, Jun. 11, 1993; Act No. 5116, Dec. 29, 1995; Act No. 5285, Jan. 13, 1997; Act No. 7709, Dec. 7, 2005>
1.
Housing site development works (including housing site preparation works; hereinafter the same shall apply);
2.
Industrial complex preparation works;
3.
Deleted;
<by Act No. 4563, Jun. 11, 1993>
4.
Tourism park preparation works;
5.
Urban environment rearrangement works (excluding the cases of constructing factories);
6.
Distribution complex preparation works;
7.
Spa development works;
8.
Passenger automobile terminal works and freight terminal works;
9.
Golf course construction works;
10.
Projects accompanied by the change of land category and which are as determined by the Presidential Decree; and
11.
Works, etc. which are similar to those of subparagraphs 1 through 9 and which are determined by the Presidential Decree.
(2)
Matters necessary for the scope and scale, etc. of the development works of any subparagraph of paragraph (1) shall be prescribed by the Presidential Decree.
법령보기 화면
Article 6 (Obligor for Payment)
(1)
The project operator falling under any of subparagraphs of
Article 5
(1) shall be under obligation to pay the development charges under the conditions as determined by this Act:
Provided
, That in case of any of the following subparagraphs, the person falling thereunder shall be under obligation to pay the development works:
1.
Person who entrusts or puts out to contract, where the development works are entrusted or contracted;
2.
Landowner, where the development works are executed by renting land owned by others; and
3.
Person who succeeds to the status of the project operator or to the
status of other person falling under subparagraph 1 or 2 before completing the development works.
(2)
Where the person, who shall pay the development charges, is in a partnership as prescribed by the Presidential Decree and falls under any of the following cases, the partners (in case where the partnership is dissolved, referring to the partners at the time of the dissolution) shall pay the development charges under the conditions as prescribed by the Presidential Decree:
<Amended by Act No. 6202, Jan. 21, 2000>
1.
Where the partnership is dissolved; and
2.
Where the property of the partnership is not sufficient for appropriating the development charges or additional dues which are imposed on the partnership or which the partnership is liable to pay.
(3)
The provisions of
Articles 23 through 25
and
38 through 41 of the Framework Act on National Taxes
shall apply
mutatis mutandis
to the succession of legal obligation to pay development charges, legal obligation to pay joint obligations and the secondary obligation for payment.
[This Article Wholly Amended by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 7 (Imposition Exception and Reduction or Exemption)
(1)
The development charges shall not be imposed on the development works executed by the State and the development works as determined by the Presidential Decree for public purposes executed by the local government.
(2)
50/100 of the development charges shall be reduced or exempted from the development works falling under any of the following subparagraphs. In this case, the provisions of each subparagraph shall not apply in duplication:
<Amended by Act No. 4563, Jun. 11, 1993; Act No. 5285, Jan. 13, 1997; Act No. 6841, Dec. 30, 2002; Act No. 6916, May 29, 2003>
1.
The works which are executed by the local government and which do not fall under paragraph (1);
2.
The works which are executed by the public agencies as determined by the Presidential Decree such as government-invested institutions under the
Framework Act on the Management of Government-Invested Institutions
, local public enterprises under the Local Public Enterprises Act and public enterprises by special Acts, and which are as determined by the Presidential Decree;
3.
The factory lot preparation works which are executed by small and medium enterprises referred to in
Article 2 (1) of the Framework Act on Small and Medium Enterprises
(hereinafter referred to as "small and medium enterprises") and industrial complex preparation works which are executed to be occupied by small and medium enterprises, except the works which are executed in the Seoul Metropolitan area referred to in subparagraph 1 of
Article 2 of the Seoul Metropolitan Area Readjustment Planning Act
;
4.
The housing site development works which are executed to construct the national housing referred to in subparagraph 3 of
Article 2 of the Housing Act
; and
5.
The works whose area of quasi-preserved mountainous district referred to in Article 4 (1) 2 of the Management of Mountainous Districts Act is exceeding 70/100 of the gross area of development works and which are as determined by the Presidential Decree.
(3)
Notwithstanding the provisions of paragraph (2), the industrial complex development works (excluding the industrial complexes located in the Seoul Metropolitan area referred to in subparagraph 1 of
Article 2 of the Seoul Metropolitan Area Readjustment Planning Act
) under the
Industrial Sites and Development Act
shall be exempt from the development charges.
<Added by Act No. 5285, Jan. 13, 1997>
Section 2 Standards for Imposition and Imposition Rate
법령보기 화면
Article 8 (Standards for Imposition)
The standards for imposition of development charges shall be the amount calculated by deducting any of the following amounts from the equivalent value of land subject to imposition at the end point of time of imposition (hereinafter referred to as the "land price at the end point of time"):
<Amended by Act No. 4563, Jun. 11, 1993>
1.
Equivalent value of land subject to imposition at the starting point of time of imposition (hereinafter referred to as the "land price at the starting point of time");
2.
Increase in normal land prices during the period of imposition; and
3.
Development costs referred to in
Article 11
.
법령보기 화면
Article 9 (Base Point)
(1)
The starting point of time of imposition shall be the date when the project operator obtains authorization, etc. of development works from the State or local government:
Provided
, That the starting point of time of imposition shall be the day falling under any of the following cases:
<Amended by Act No. 4563, Jun. 11, 1993; Act No. 6202, Jan. 21, 2000>
1.
Date of acquisition on which the land-use plan, etc. as determined by the Presidential Decree is modified before obtaining authorization, etc. and where the land is acquired before the modification of the landuse plan, etc.:
Provided
, That in case the land-use plan, etc. is modified after the elapse of two years from the date of acquisition or other cases as determined by the Presidential Decree, the starting point of time of imposition shall be the date as prescribed by the Presidential Decree;
2.
Deleted; and
<by Act No. 5586, Dec. 28, 1998>
3.
Point of time as determined by the Presidential Decree where the area of land subject to imposition is modified due to the modification of authorization, etc.
(2)
The date on which authorization etc. of the development works is obtained and date of acquisition referred to in paragraph (1) shall be determined by the Presidential Decree.
<Amended by Act No. 4563, Jun. 11, 1993>
(3)
The end point of time of imposition shall be the date on which authorization etc. of completion of the development works is obtained from the State or local government pursuant to related Acts and subordinate statutes:
Provided
, That where all or part of the land subject to imposition falls under any of the following subparagraphs, the date falling under any of the following subparagraphs shall be the end point of time of imposition for the land concerned:
<Amended by Act No. 4563, Jun. 11, 1993>
1.
Where part of the land subject to imposition is completed pursuant to related Acts and subordinate statutes;
2.
Where the person obliged to pay tax starts to use for uses and purposes of development works or makes a disposal such as sale in lots to other persons and which is as determined by the Presidential Decree; and
3.
Other cases as determined by the Presidential Decree.
(4)
The date on which authorization, etc. of the development works is obtained referred to in the main sentence of paragraph (3) shall be determined by the Presidential Decree.
<Added by Act No. 4563, Jun. 11, 1993>
법령보기 화면
Article 10 (Calculation of Land Prices)
(1)
The land price at the end point of time referred to in
Article 8
shall be the aggregate amount of the value calculated on the comparative Table referred to in Article 9 (2) of the Public Notice of Values and Appraisal of Real Estate Act on the basis of the officially assessed land price of the standard land most similar in the utilization situations to the land subject to imposition at the end point of imposition and the increased value in normal land prices from the first of January of the year concerned to the end point of time of imposition.
<Amended by Act No. 5409, Aug. 30, 1997; Act No. 7335, Jan. 14, 2005>
(2)
Where determined by the Presidential Decree such as obtaining authorization, etc. from the State or the local government about the disposal price, in making a disposal such as sale of the land subject to imposition in lots, the disposal price may, notwithstanding the provisions of paragraph (1), be the land price at the end point of time under the conditions as determined by the Presidential Decree.
(3)
The land price at the starting point of time in subparagraph 1 of
Article 8
shall be the value which is calculated by adding the increase in normal land price from the basic date of the publicized individual land price to the starting point of time of imposition, to such publicized land price (referring to the land price publicized most recently from the starting point of time of imposition) of the land subject to imposition in the year under which the starting point of time of imposition falls:
Provided
, That in the following cases, the land price at the starting point of time may be the amount which is calculated by adding or deducting the increase in normal land price from the date of purchase or acquisition to the starting point of time of imposition, to the actual purchase or acquisition price:
<Amended by Act No. 5572, Sep. 19, 1998; Act No. 6656, Feb. 4, 2002: Act No. 6832, Dec. 26, 2002>
1.
Where the land is purchased from the State, local government, or an agency determined by the Ministerial Decree of Construction and Transportation;
2.
Where the land is purchased by means of auction or bidding;
3.
Where the land is purchased by a local government or a public agency referred to in
Article 7
(2) 2;
4.
Where the land is purchased through consultation or expropriation under the
Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor
; and
5.
Where the actual purchase price of the land is objectively recognized as a normal sale price, as determined by the Presidential Decree.
<This Paragraph, which was decided by the Constitutional Court as limited unconstitutionality on June 25, 1998, is amended under Act No. 5572, September 19, 1998>
(4)
In calculating the land price at the end point of time and the land price at the starting point of time referred to in paragraph (1) or (3), the land which has been contributed to the State or the local government or the state or public land is included in the land subject to imposition, it shall be excluded from the calculated area of the land price at the end point of time and the land price of the starting point of time.
(5)
In calculating the land price at the end point of time and the land price at the starting point of time referred to in paragraphs (1) and (3), where determined by the Presidential Decree when no officially individual assessed land prices of the land concerned exist, it shall be calculated according to the methods as determined by the Ministerial Decree of Construction and Transportation.
<Amended by Act No. 5285, Jan. 13, 1997>
(6)
Any person obliged to pay who desires to follow the provisions of the proviso of paragraph (3) with respect to the land price at the starting point of time, shall submit materials certifying the veracity of any of subparagraphs of the same paragraph to the Minister of Construction and Transportation within the period specified by the Ministerial Decree of Construction and Transportation.
<Added by Act No. 5572, Sep. 19, 1998>
[This Article Wholly Amended by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 11 (Calculation of Development Costs)
(1)
The development costs referred to in subparagraph 3 of
Article 8
shall be calculated by adding together the amounts of any of the following subparagraph paid in connection with the execution of the development works:
<Amended by Act No. 4563, Jun. 11, 1993>
1.
Net construction cost (including taxes and public charges), research expenditure, design cost, general management expenses and other expenses;
2.
Equivalent value where the person obliged to pay contributes or donates public facilities or land, etc. to the State or the local government under the provisions of related Acts and subordinate statutes or conditions of authorization; and
3.
Cost for reclamation of the land concerned.
(2)
Matters necessary for the calculation methods, etc. of each subparagraph of paragraph (1) shall be determined by the Presidential Decree.
법령보기 화면
Article 12 (Recognition of Development Costs of Transfer Income Tax Amount, etc.)
(1)
Where the transfer income tax is imposed on the income accruing from the transfer of land or business, etc. after the starting point of time of imposition and before the imposition of development charges, the tax amount equivalent to that from the starting point of time of imposition until the point of time of transfer, etc. from among the said tax amount may, notwithstanding the provisions of
Article 11
, be represented in the development costs referred to in the said Article.
<Amended by Act No. 4563, Jun. 11, 1993; Act No. 6558, Dec. 31, 2001>
(2)
The scope, etc. of tax amount to be represented in the development costs pursuant to paragraph (1) shall be determined by the Presidential Decree.
법령보기 화면
Article 13 (Imposition Rate)
The development charges to be paid by a person obliged to pay shall be 25/100 of the development gains calculated pursuant to
Article 8
:
Provided
, That as for the development works to be executed in the development restriction area under
Article 38 of the National Land Planning and Utilization Act
, the development charges shall be 20/100 of the development gains if the person obliged to pay is the landowner at the time of the designation of the said area.
<Amended by Act No. 4563, Jun. 11, 1993; Act No. 5409, Aug. 30, 1997; Act No. 5572, Sep. 19, 1998; Act No. 6655, Feb. 4, 2002>
Section 3 Imposition and Collection
법령보기 화면
Article 14 (Determination and Imposition of Charges)
(1)
The Minister of Construction and Transportation shall determine and impose the development charges within 3 months from the end point of time of imposition:
Provided
, That where the land falls under the proviso of
Article 9
(3) and where the project concerned corresponds to the part of the large-scale project and it cannot submit the specifications of development costs referred to in
Article 11
, the development charges may be determined and imposed under the conditions as determined by the Presidential Decree.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
Where the Minister Construction and Transportation intends to determine and impose the development charges pursuant to paragraph (1), he shall notify the person obliged to pay the charges in advance.
<Amended by Act No. 5285, Jan. 13, 1997>
(3)
The person who has objections against the development charges notified pursuant to paragraph (2) may request an investigation under the conditions as determined by the Presidential Decree.
[This Article Wholly Amended by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 15 (Notice for Payment)
(1)
Where the Minister of Construction and Transportation decides to impose the development charges under this Act, he shall issue a notice of payment to the person obliged to pay under the conditions as determined by the Presidential Decree.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
The development charges shall not be imposed after an elapse of 5 years from the date on which they can be imposed and notified. In this case, the development charges may be corrected and imposed or other necessary dispositions may be taken not later than an elapse of 1 year from the date on which a decision or judgement by an administrative appeal or a litigation becomes fixed.
<Added by Act No. 4563, Jun. 11, 1993; Act No. 6832, Dec. 26, 2002>
(3)
The date on which the development charges can be imposed and notified shall be determined by the Presidential Decree.
<Added by Act No. 6832, Dec. 26, 2002>
법령보기 화면
Article 15-2 (Additional Collection)
(1)
Where there exist causes as determined by the Presidential Decree such as not using the land for uses and purposes of development works concerned within the period as determined by the Presidential Decree without special causes after executing the works subject to reduction or exemption of development charges (including the works as objects of reduction or exemption as determined by other Acts) pursuant to
Article 7
(2) and (3), the reduced or exempted development charges shall be collected.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
Matters necessary for the collection of development charges referred to in paragraph (1) shall be determined by the Presidential Decree.
[This Article Added by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 15-3 (Prescription)
(1)
When a right to collect the development charges and a right to claim a refund of erroneously paid amount are not exercised for 5 years from the time they may be exercised, extinctive prescription shall be completed.
(2)
The extinctive prescription of a right to collect the development charges under paragraph (1) shall be interrupted by a reason falling under the following subparagraphs:
1.
Notice for payment;
2.
Reminder for Payment;
3.
Request for issuance; and
4.
Seizure.
(3)
The extinctive prescription interrupted under paragraph (2) shall proceed anew from the time when a period falling under the following subparagraphs elapses:
1.
Payment period as noticed;
2.
Payment period as reminded;
3.
Period in the course of request for issuance; and
4.
Period by the release of seizure.
(4)
The extinctive prescription of a right to collect the development charges under paragraph (1) shall not proceed during the period for postponement of payment or payment by allotment.
(5)
The extinctive prescription of a right to claim a refund under paragraph (1) shall be interrupted by an exercise of the right to claim a refund.
(6)
Except for the provisions provided under this Act regarding extinctive prescription, the provisions of the
Civil Act
shall be applied
mutatis mutandis
.
[This Article Added by Act No. 6832, Dec. 26, 2002]
법령보기 화면
Article 16 (Payment)
(1)
The person obliged to pay the development charges shall pay the development charges within 6 days from the date of imposition.
(2)
The development charges shall be, in principle, paid in cash, but the payment in the land subject to imposition concerned and land similar to this (hereinafter referred to as the "payment in kind") may be recognized.
<Amended by Act No. 4563, Jun. 11, 1993>
(3)
The standards and procedures for payment in kind referred to in paragraph (2) and other matters necessary for payment in kind shall be determined by the Presidential Decree.
법령보기 화면
Article 16-2 (Collection before Date of Payment)
(1)
Where the person obliged to pay has causes falling under any of the following subparagraphs, the Minister of Construction and Transportation may collect the development charges already imposed before the date of payment:
<Amended by Act No. 5285, Jan. 13, 1997>
1.
Where the disposition for arrears has been made against the national and local taxes or public charges;
2.
Where he has received the compulsory execution;
3.
Where he has received the adjudication of bankruptcy;
4.
Where the official auction against him has commenced;
5.
Where the juristic person has dissolved;
6.
Where deemed that he has performed acts to evade the development charges; and
7.
Where he has no manager for payment of development charges and has no address or temporary domicile within the State.
(2)
Where the Minister of Construction and Transportation intends to collect before the date of payment pursuant to paragraph (1), he shall specify the date of payment and notify the person obliged for payment of the purpose and the modification of date of payment, etc.
<Amended by Act No. 5285, Jan. 13, 1997>
[This Article Added by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 17 (Postponement of Payment and Payment in Installments)
(1)
Where deemed difficult for the person obliged for payment of the development charges to pay the development charges due to causes falling under any of the following subparagraphs, the Minister of Construction and Transportation may authorize the deferment of the date of payment within the scope of 3 years or the payment in installments within the scope of 5 years, taking account of the utilization situations according to the purpose of development works concerned under the conditions as determined by the Presidential Decree:
<Amended by Act No. 5285, Jan. 13, 1997; Act No. 5572, Sep. 19, 1998>
1.
Where he suffers heavy losses on assets due to disaster or theft;
2.
Where he suffers serious losses on business;
3.
Where he faces grave crisis from business;
4.
Where the person obliged for payment or his family living together requires a long-term treatment due to his disease or serious injury; and
5.
Other cases as determined by the Presidential Decree.
(2)
Where the person obliged for payment intends to receive authorization for the deferment of date of payment or payment in installments of the development pursuant to paragraph (1), he shall make an application to the Minister of Construction and Transportation under the conditions as determined by the Presidential Decree.
<Amended by Act No. 5285, Jan. 13, 1997>
(3)
The Minister of Construction and Transportation shall collect the development charges by adding the amount equivalent to the interest rates of term deposits for the deferred period of payment or for the grace period due to payment in installments in case of paragraphs (1) and (2).
<Amended by Act No. 5285, Jan. 13, 1997>
[This Article Wholly Amended by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 18 (Demand for Payment)
(1)
Where the person obliged for payment of the development charges fails to pay them in full within the period as specified pursuant to
Article 16
(1), the Minister of Construction and Transportation shall issue a demand note within 10 days after the expiration of time limit for payment.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
The provisions of
Articles 21
and
22 of the National Tax Collection Act
shall apply
mutatis mutandis
to a case where the development charges or the development charges in arrears are paid in full within the time limit for payment.
법령보기 화면
Article 19 (Disposition for Arrears, etc.)
(1)
Where the person obliged for payment of the development charges receives a demand note and fails to pay the development charges and additional dues, etc. in full within the designated time limit, the Minister of Construction and Transportation may collect them pursuant to the example of the disposition on default of national taxes.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
The development charges or additional dues, etc. under paragraph (1) shall be collected with priority over other claims except for the national tax and local tax:
Provided
, That this shall not apply to a claim guaranteed by a registered lease on deposit basis, a pledge or a mortgage in the cases where the development charges and additional dues, etc. are collected from the proceeds of the sale of a property in which the fact that the settlement of the registered lease on deposit basis, the pledge or the mortgage was made before the date of the notice for payment of the development charges under
Article 15
is verified.
<Added by Act No. 6832, Dec. 26, 2002>
(3)
In collecting the development charges which authorize the payment in installments, where the payment in installments is in arrears once notwithstanding the provisions of
Article 17
(1), the whole amount of the development charges to be paid in installments after the period for payment and additional dues, etc. shall be collected in mass at the time of the disposition for arrears.
법령보기 화면
Article 19-2 (Deficit Disposal)
(1)
When there exists a reason falling under the following subparagraphs to a defaulter, the Minister of Construction and Transportation may take a deficit disposal:
1.
Where the disposition for arrears is terminated and the alloted amount appropriated to the amount in arrears is short of such amount in arrears;
2.
Where extinctive prescription is completed under
Article 15-3
;
3.
Where no balance is expected after an estimated value of the total property which is the object of the disposition for arrears is appropriated to disposition fee for arrears; and
4.
Where there exists no expectation to collect the amount in arrears as the whereabouts of the defaulter is unknown or he is proved to have no property.
(2)
When the Minister of Construction and Transportation finds other property which may be seized after the deficit disposal under paragraph (1), he shall revoke the disposal without delay and take a disposition for arrears:
Provided
, That this shall not apply when it falls under paragraph (1) 2.
[This Article Added by Act No. 6832, Dec. 26, 2002]
법령보기 화면
Article 20 (Duty to Present Data)
The person obliged for payment shall present the specifications necessary for the calculation of the development costs referred to in
Article 11
to the Minister of Construction and Transportation, under the conditions as determined by the Ministerial Decree of Construction and Transportation according to the classification of any of the following subparagraphs:
<Amended by Act No. 5285, Jan. 13, 1997>
1.
Where he obtains authorization, etc. of completion of the development works from the State or the local government; and
2.
In case of the proviso of
Article 9
(3).
[This Article Wholly Amended by Act No. 4563, Jun. 11, 1993]
법령보기 화면
Article 21 (Notification of Data)
(1)
An administrative agency which grants authorization, etc. on the development works subject to imposition of the development charges shall notify the Minister of Construction and Transportation of the fact within 15 days from the date on which it grants authorization, etc.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
Where the Minister of Construction and Transportation imposes the development charges, he shall notify matters concerning the projects of object, person obliged for payment, amount of imposition, project period, and the date of imposition, etc. to the Administrator of National Tax Administration within 15 days from the date of imposition under the conditions as determined by the Ministerial Decree of Construction and Transportation.
<Amended by Act No. 5285, Jan. 13, 1997>
CHAPTER III SUPPLEMENTARY PROVISIONS
법령보기 화면
Article 22 (Special Cases of Administrative Appeals)
(1)
A person who has objections against the imposition and collection of the development charges, etc. may ask the Central Land Expropriation Commission under the
Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor
for administrative appeals.
<Amended by Act No. 6656, Feb. 4, 2002>
(2)
Deleted.
<by Act No. 5572, Sep. 19, 1998>
(3)
Notwithstanding the provisions of
Articles 5
and
6 of the Administrative Appeals Act
, the Central Land Expropriation Commission under the
Act on the Acquisition of Land, etc. for Public Works and the Compensation Therefor
shall deliberate and adjudicate by resolution on the administrative appeals referred to in paragraph (1).
<Amended by Act No. 4563, Jun. 11, 1993; Act No. 5572, Sep. 19, 1998; Act No. 6656, Feb. 4, 2002>
법령보기 화면
Article 23 (Delegation of Powers)
(1)
The Minister of Construction and Transportation may delegate part of the powers (excluding the powers on the imposition and collection of development charges) provided under this Act to the Special Metropolitan City Mayor, Metropolitan City Mayor or
Do
governor under the conditions as determined by the Presidential Decree.
<Amended by Act No. 5285, Jan. 13, 1997>
(2)
The Minister of Construction and Transportation may delegate the powers on the determination, imposition and collection of development charges provided under this Act to the head of
Si
/
Gun
/
Gu
(limited to the head of the autonomous Gu). In this case, he may grant the fees of delegation to the local government concerned within the scope of actual expenses for collecting them under the conditions as determined by the Presidential Decree.
<Amended by Act No. 5285, Jan. 13, 1997; Act No. 6832, Dec. 26, 2002>
법령보기 화면
Article 24 (Penal Provisions)
(1)
A person who concludes a false contract for the purpose of evading or reducing the development charges or for the purpose of having them evaded or reduced shall be punished by imprisonment not more than 3 years or a fine equivalent to not more than three times the development charges which he has evaded or reduced or attempted to evade or reduce.
(2)
Where the representative of a juristic person, or an agent, servant or employee of a juristic person or an individual commits violation as referred to in paragraph (1), such juristic person or individual shall also be punished by a fine as referred to in paragraph (1) in addition to punishing the offender.
법령보기 화면
Article 25 (Fine for Negligence)
(1)
A person who fails to present or falsely presents the specifications referred to in
Article 20
shall be punished by a fine for negligence not exceeding 2 million won.
(2)
The fine for negligence referred to in paragraph (1) shall be imposed and collected by the Minister of Construction and Transportation under the conditions as determined by the Presidential Decree.
<Amended by Act No. 5285, Jan. 13, 1997>
(3)
A person who is dissatisfied with the disposition of the fine for negligence referred to in paragraph (2) may make an objection to the Minister of Construction and Transportation within 30 days from the date on which notice of the disposition is received by him.
<Amended by Act No. 5285, Jan. 13, 1997>
(4)
Where the person who has been subject to the disposition of the fine for negligence referred to in paragraph (2) makes an objection pursuant to paragraph (3), the Minister of Construction and Transportation shall notify without delay the fact to the competent court, and the competent court to which has been notified shall bring the case of the fine for negligence to trial under the
Non-Contentious Case Litigation Procedure Act
.
<Amended by Act No. 5285, Jan. 13, 1997>
(5)
Where no objection is made, or no fine for negligence is paid within the period referred to in paragraph (3), it shall be collected following the example of the disposition on default of national taxes.
ADDENDA
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 1990.
Article 2 (Transitional Measures)
(1)
The projects of which the execution has not been completed during the development works subject to imposition of the development charges referred to in
Article 5
at the time this Act enters into force shall be also applied by this Act.
(2)
The development charges for the projects in paragraph (1) shall be calculated by dividing the amount corresponding to the period of project implementation after this Act enters into force from the base amount of imposition calculated pursuant to
Article 8
for the period of all project implementation including the period of project implementation prior to entry into force of this Act.
[This Article Wholly Amended by Act No. 4563, Jun. 11, 1993]
Article 3 Omitted.
ADDENDA<Act No. 4434, Dec. 14, 1991>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 5 Omitted.
ADDENDA<Act No. 4563, Jun. 11, 1993>
Article 1 (Enforcement Date)
This Act shall enter into force two months after the date of its promulgation.
Article 2 (Examples of Application on Subjects, etc. of Imposition of Development Charges)
(1)
The amended provisions of
Articles 5
,
9
(1) and
10
(5) shall apply starting from the project commencing with authorization, etc. of projects after this Act enters into force.
(2)
The amended provisions of
Articles 6
,
9
(3),
10
(3),
14
,
15-2
,
16-2
,
17
,
20
, and
22
shall apply starting from the project completed after this Act enters into force.
(3)
The amended provision of
Article 10
(1) shall be applied starting from the project calculating land price at the end point of time after this Act enters into force.
(4)
The amended provisions of
Article 16
, and Article 2 of the addenda of the Act No. 4175, the Restitution of Development Gains Act shall apply starting from the project which imposes the development charges after this Act enters into force.
Article 3 (Examples of Application of Starting Point of Time of Imposition)
In applying the amended provisions of
Article 9
(1), the date of acquisition for the land owned before this Act enters into force shall be the enforcement date of this Act.
Article 4 Omitted.
ADDENDA<Act No. 5108, Dec. 29, 1995>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 8 Omitted.
ADDENDA<Act No. 5116, Dec. 29, 1995>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 15 Omitted.
ADDENDA<Act No. 5285, Jan. 13, 1997>
(1)
(Enforcement Date) This Act shall enter into force on the date of its promulgation.
(2)
(Applicable Cases on Reduction and Exemption of Development Charges) The amended provisions of
Article 7
(2) and (3) shall apply starting from the project for which 3 months have not elapsed from the end point of time of imposition and on which the development charges have not been imposed at the time this Act enters into force.
ADDENDA<Act No. 5409, Aug. 30, 1997>
(1)
(Enforcement Date) This Act shall enter into force on the date of its promulgation.
(2)
(Transitional Measures as to Calculation of Land Prices) The calculation of land prices in respect of works subject to the imposition of development charges before this Act enters into force shall be governed by the previous provisions, regardless of the amended provisions of
Article 10
.
(3)
(Applicable Cases on Imposition of Development Charges) The amended provisions of
Article 13
shall apply to such parts of works as are completed after this Act enters into force.
ADDENDA<Act No. 5572, Sep. 19, 1998>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation:
Provided
, That the amended provisions of the main sentence of
Article 13
shall enter into force on January 1, 2000.
Article 2 (Applicable Cases on Imposition Rate of Development Charges)
The amended provisions of the main sentence of
Article 13
shall apply to the development projects authorized on or after January 1, 2000.
Article 3 (Special Cases on Exemption from Development Charges)
(1)
Notwithstanding the provisions of
Article 3
(1), the development projects, authorized prior to December 31, 1999, to be subject to the imposition of the development charges referred to in
Article 5
of this Act shall be exempted from the development charges.
(2)
The provisions of paragraph (1) shall apply to the projects on which the development charges have failed to be imposed, and for which three months have not passed since the end of imposition at the time this Act enters into force.
Article 4 (Transitional Measures on Deferment of Date of Payment)
A person for whom the date of payment of development charges has been deferred and the deferred date of payment has not been closed, or for whom the deferment of the date of payment is in the course of application, under the previous provisions at the time this Act enters into force, may apply for the deferment of the date of payment under the amended provisions of
Article 17
(1). In this case, the deferment period of the date of payment shall not exceed three years in total.
ADDENDA<Act No. 5586, Dec. 28, 1998>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation.
Articles 2 and 3 Omitted.
ADDENDA<Act No. 6202, Jan. 21, 2000>
(1)
(Enforcement Date) This Act shall enter into force three months after the date of its promulgation.
(2)
(Applicable Cases on Payment of Development Charges) The amended provision of
Article 6
(2) 2 shall apply starting from the development charges imposed after this Act enters into force.
ADDENDA<Act No. 6558, Dec. 31, 2001>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2002. (Proviso Omitted.)
Articles 2 through 25 Omitted.
ADDENDA<Act No. 6655, Feb. 4, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2003.
Articles 2 through 25 Omitted.
ADDENDA<Act No. 6656, Feb. 4, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2003.
Articles 2 through 12 Omitted.
ADDENDUM<Act No. 6832, Dec. 26, 2002>
This Act shall enter into force on the date of its promulgation.
ADDENDA<Act No. 6841, Dec. 30, 2002>
Article 1 (Enforcement Date)
This Act shall enter into force nine months after the date of its promulgation.
Articles 2 through 12 Omitted.
ADDENDA<Act No. 6916, May 29, 2003>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.)
Articles 2 through 13 Omitted.
ADDENDA<Act No. 7061, Jan. 16, 2004>
Article 1 (Enforcement Date)
This Act shall enter into force on April 1, 2004:
Provided
, That …(Omitted.)… the provisions of
Article 5
shall enter into force on January 1, 2005.
Articles 2 through 4 Omitted.
Article 5 (Amendment of Other Acts)
ADDENDA<Act No. 7335, Jan. 14, 2005>
Article 1 (Enforcement Date)
This Act shall enter into force on the date of its promulgation.
Articles 2 through 12 Omitted.
ADDENDA<Act No. 7709, Dec. 7, 2005>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 2006.
Article 2 (Special Example for Collection of Development Charges)
Notwithstanding the provisions of
Article 3
, the State shall not collect development charges from January 1, 2002 to December 31, 2005 for the development gains accruing in the regions other than the region of Seoul Special Metropolitan City,
Incheon
Metropolitan City and
Gyeonggi-do
where the works subject to the imposition of development charges are implemented under
Article 5
, and from January 1, 2004 to December 31, 2005 for the development gains accruing in the region of Seoul Special Metropolitan City,
Incheon
Metropolitan City and
Gyeonggi-do
, from the works for which authorization, etc. was obtained respectively.
Article 3 Omitted.
Last updated : 2009-07-26