Article 1 (Purpose)
The purpose of this Act is to simplify the procedures necessary for execution of the project to establish, relocate, and expand the elementary, middle, high, and special school facilities, prescribe special cases relating to building permission, etc., and facilitate the establishment, relocation and expansion of school facilities, thereby contributing to the improvement of the educational environment and the enhancement of the quality of education.
<Amended by Act No. 4881, Jan. 5, 1995; Act No. 5069, Dec. 29, 1995>
법령보기 화면
Article 2 (Definitions)
The definitions of terms used in this Act shall be as follows:
<Amended by Act No. 6210, Jan. 28, 2000>
1.
The term “school facilities” means facilities falling under each of the following items: and
(a)
Sites of school buildings, playgrounds and practice areas;
(b)
School buildings, gymnasiums, dormitories and feeding facilities; and
(c)
Other facilities, prescribed by the Presidential Decree, which are installed primarily for the purpose of learning support;
2.
The term “school facilities project” means a project designed to install, relocate or expand school facilities.
법령보기 화면
Article 3 (Scope of Application)
Schools to which this Act applies (hereinafter referred to as the “school”) shall be elementary, middle, high, and special schools.
<Amended by Act No. 5069, Dec. 29, 1995>
법령보기 화면
Article 4 (Approval, etc. of Plan for School Facilities Project)
(1)
The person who intends to undertake a school facilities project (except the State and local government) shall prepare the plan for school facilities project execution (hereinafter referred to as the “execution plan”) including the site of execution, size, and financial resources of the school facilities project as prescribed by the Presidential Decree and obtain approval from the supervisory organ referred to in
Article 6 of the Elementary and Secondary Education Act
(hereinafter referred to as the “supervisory authority”):
Provided
, That this shall not apply to the execution plan, when construction, building, large-scale repair or alteration of use (hereinafter referred to as the “construction, etc.”) is intended for school facilities within the school facilities project execution site that has passed the completion inspection referred to in
Article 13
(2) upon completion of the school facilities project.
<Amended by Act No. 6210, Jan. 28, 2000>
(2)
The person who intends to modify the plan approved as referred to in the main text of paragraph (1) shall obtain the supervisory authorities’ approval for modification:
Provided
, That the approval shall not be required for trivial modificaion determined by the Presidential Decree.
(3)
In approving the plan or the modification plan under paragraph (1) or (2), the supervisory authority shall, under the conditions as prescribed by the Presidential Decree, consult in advance with the heads of the competent administrative agencies that have jurisdiction over the applicable matters of each subparagraph of
Article 5
.
(4)
In executing a school facilities project, the State or local government shall prepare the execution plan and consult with the heads of the competent administrative agencies that have jurisdiction over the applicable matters of each subparagraph of
Article 5
, as prescribed by the Presidential Decree:
Provided
, That this shall not apply with regard to any execution plan for a case in which construction, etc. of school facilities is intended within a school facilities project execution site where the school facilities project has been already completed.
(5)
The matters that shall be included in the execution plan referred to in paragraphs (1) and (4) shall be determined by the Presidential Decree.
(6)
In a case where the supervisory authority intends to approve the plan or the modification plan under paragraph (1) or (2), or where the State or local government intends to prepare the execution plan as prescribed in paragraph (4), it shall hear the opinions of the interested persons, such as the land owner, etc. when there are rights besides the ownership of the land, buildings and other fixtures on the land necessary for the expropriation or utilization under
Article 10
.
(7)
In a case where the supervisory authority approves the plan or themodification plan under paragraph (1) or (2), the consulted agencies referred to in paragraph (3) and interested persons shall be notified, and the public notification of the fact shall be made immediately. The same shall apply when the State or local government completes the consultation referred to in paragraph (4).
(8)
The person who intends to execute a school facilities project may apply simultaneously for the approval of the plan or modification plan referred to in paragraph (1) or (2) and the approval for construction, etc. of school facilities referred to in
Article 5-2
(1).
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 5 (Relation with Other Acts)
In a case where the person who intends to execute a school facilities project has obtained the approval of the plan or modification plan under
Article 4
(1) or (2), or has completed a consultation under paragraph (4) of the same Article, he shall be considered to have permission, authorization, approval, designation, agreement, consultation, report, or cancellation of the applicable matters from among the following subparagraphs:
<Amended by Act No. 4429, Dec. 14, 1991; Act No. 4881, Jan. 5, 1995; Act No. 5454, Dec. 13, 1997; Act No. 5893, Feb. 8, 1999>
1.
Consultation on or approval of the establishment of public facilities referred to in
Article 20 of the Act on the Utilization and Management of the National Territory
;
2.
Permission for acts referred to in
Article 4 of the Urban Planning Act
, designation of the project undertaker for the urban planning project referred to in
Article 23
of the same Act, and authorization of the execution plan for the urban planning project referred to in
Article 25
of the same Act;
3.
Consultation on or approval of a state project as referred to in
Article 8 of the Road Act
, execution permission for road construction for a person who is not the administrative agency referred to in
Article 34
of the same Act, and permission to occupy a road as referred to in
Article 40
of the same Act;
4.
Deleted;
<by Act No. 4881, Jan. 5, 1995>
5.
Consultation on, approval of, or permission for the public sewerage project or its construction referred to in
Articles 3 and 13 of the Sewerage Act
;
6.
Permission to occupy and use a public park as referred to in
Article 23 of the Natural Parks Act
, permission for activities in the public park protection area as referred to in
Article 25
of the same Act, and consultation on a state project as referred to in
Article 50
(1) of the same Act;
7.
Permission for conversion of farmlands as referred to in
Article 36 (1) of the Farmland Act
;
8.
Deleted;
<by Act No. 5454, Dec. 13, 1997>
9.
Permission for, agreement on, and consultation on diversion of a conserved forest referred to in
Article 18 of the Forestry Act
, cancellation of the designation of a reserved forest as referred to in
Article 57
of the same Act, permission for timber-cutting in a reserved forest as referred to in
Article 62
of the same Act, and permission and report for cutting any standing timber as referred to in
Article 90
(1) of the same Act;
10.
Permission for timber-cutting in the erosion control area referred to in Article 14 of the Work against Land Erosion or Collapse Act and cancellation of the designation of the erosion control area as referred to in
Article 20-2
of the same Act;
11.
Permission for changes in the configuration and quality of land as referred to in
Article 39 of the Land Compartmentalization and Rearrangement Projects Act
; and
12.
Permission for occupation and use of the river, etc. as referred to in
Article 33 of the River Act
.
법령보기 화면
Article 5-2 (Construction, etc. of School Facilities)
(1)
When the person who has obtained the approval or modification approval for the execution plan under
Article 4
(1) or (2) intends to construct school facilities, he shall obtain the approval of or report it to the supervisory authority under the conditions as prescribed by the Presidential Decree, notwithstanding the provisions of
Articles 8 and 9 of the Building Act
. The same shall apply where he intends to construct school facilities under the proviso of
Article 4
(1).
(2)
When the supervisory authority has granted the approval or received the report under paragraph (1), it shall notify the head of
Si
/
Gun
/
Gu
(limited to the head of the autonomous
Gu
; hereinafter the same shall apply) of the matters concerning it.
(3)
When the State or local government intends to construct school facilities, it shall notify the head of
Si
/
Gun
/
Gu
of the matters concerning it, notwithstanding the provisions of
Article 25 (1) of the Building Act
.
(4)
When the State, local government, or a supervisory authority has notified the head of
Si
/
Gun
/
Gu
of the matters concerning the construction, etc. of school facilities under paragraph (2) or (3), he shall be considered to have obtained the building permission or the building report referred to in
Article 8
or
9 of the Building Act
, or to have consulted with the head of
Si
/
Gun
/
Gu
under
Article 25 (1) of the Building Act
.
<Amended by Act No. 5454, Dec. 13, 1997; Act No. 6210, Jan. 28, 2000>
(5)
With respect to school facilities which are considered to have obtained the building permission or the building report, or to have consulted under paragraph (4), the supervisory authority shall grant permission, etc. in accordance with the same provisions notwithstanding the provisions of
Articles 10
,
11
,
15
(1) and (2),
16
(1),
21
,
23
,
27
(1) and
69
.
<Added by Act No. 6210, Jan. 28, 2000>
(6)
Where the supervisory authority examines whether the school facilities for which it has granted the approval and received the report under paragraphs (1) and (2) violate this Act or the
Building Act
, and considers it necessary, it shall order the necessary measure to correct the situation and notify the head of
Si
/
Gun
/
Gu
of the result.
[This Article Added by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 6 (Consultation on Activities within School Facilities)
When administrative agencies of various levels, after approval of the execution plan referred to in
Article 4
(referring to consultation in the case of the State or local government; hereinafter the same shall apply) has been obtained, plan to carry out the project falling under one of the following subparagraphs or give approval for it or other such dispositions in any school facilities (including the scheduled site for school facilities for which the execution plan has been approved under the provisions of
Article 4
), they shall consult with the supervisory authority of the school concerned:
<Amended by Act No. 4881, Jan. 5, 1995>
1.
Installation of roads, water-supply systems, sewerages, waterways, and fixtures thereon; and
2.
Excavation of the ground, reclamation, and other changes in the configuration and quality of the land.
법령보기 화면
Article 7 (Priority Given to Construction of Public Facilities)
When the execution plan as referred to in
Article 4
has been approved, the administrative agency in charge of the public facilities determined by the Presidential Decree such as roads, water-supply systems, sewerages, etc. shall make efforts to give priority to the installation of the public facilities related to the school facilities project within the limit of its budget so as to allow a smooth execution of the school facilities project.
법령보기 화면
Article 8 (Entry to and Exit from Land, etc.)
(1)
The person who obtained the approval of the execution plan as referred to in
Article 4
(hereinafter referred to as the “project undertaker”) may enter others’ land or use it temporarily in order to execute the school facilities project and, if necessary, may change or eliminate the standing trees, earth and rocks, or other obstacles.
(2)
The provisions of
Article 5 of the Urban Planning Act
shall apply
mutatis mutandis
to paragraph (1).
법령보기 화면
Article 9 (Compensation)
(1)
When there exists any person who has suffered a loss through the activities referred to in
Article 8
, the project undertaker shall compensate him for the loss.
(2)
The provisions of
Article 6 of the Urban Planning Act
shall apply
mutatis mutandis
to the compensation for the loss referred to in paragraph (1).
법령보기 화면
Article 10 (Expropriation and Utilization)
(1)
In a case where the project undertaker needs rights besides the ownership of the specific land, buildings, and other fixtures on the land within the execution site in order to execute the school facilities project, he may expropriate or use those rights besides the ownership of the land, buildings, and other fixtures on the land.
(2)
With regard to the land expropriation or utilization referred to in paragraph (1), the
Land Expropriation Act
shall apply, except when there are specific provisions in this Act.
(3)
In applying the
Land Expropriation Act
under paragraph (2), the approval of the execution plan shall be considered the approval of project referred to in
Article 14 of the Land Expropriation Act
, and the public notification referred to in
Article 4
(7) shall be considered the notification referred to in
Article 16 (1) of the Land Expropriation Act
, notwithstanding the provisions of
Articles 17 and 25 (2) of the Land Expropriation Act
, an application for adjudication shall be completed within the school facilities project execution period determined at the time of when the execution plan in approved.
<Amended by Act No. 4881, Jan. 5, 1995>
[This Article Added by Act No. 3740, Aug. 2, 1984]
법령보기 화면
Article 11 (Cancellation, etc. of Approval of Execution Plan)
(1)
When the project undertaker (excluding the project undertaker who is the State or local government; hereinafter
Articles 12
(1) and
13
(1) the same shall apply) falls under one of the following subparagraphs, the supervisory authority may cancel the approval referred to in this Act or order the modification of the execution plan or other necessary measures:
<Amended by Act No. 4881, Jan. 5, 1995>
1.
When one has obtained the approval referred to in this Act by using unjust means; and
2.
When the continued execution of the school facilities project is deemed difficult, or when there is a possibility for considerable delay.
(2)
Deleted.
<by Act No. 5453, Dec. 13, 1997>
법령보기 화면
Article 11-2 (Hearing)
Where the supervisory authority intends to cancel the approval of an execution plan under
Article 11
, it shall hold a hearing.
[This Article Added by Act No. 5453, Dec. 13, 1997]
법령보기 화면
Article 12 (Supervision, etc.)
(1)
If the supervisory authority deems it necessary for supervising, it may ask the person in charge of the construction, etc. of school facilities under the proviso of
Article 4
(1) to file a necessary report or order him to submit materials, or have the official affiliated with the supervisory authority inspect the school facilities project.
(2)
The official who performs his inspection under paragraph (1) shall present the identification card that indicates his powers to the party concerned.
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 13 (Completion Inspection, etc.)
(1)
When the project undertaker completes the school facilities project, he shall file a report thereof with the supervisory authority and undergo the inspection of completion under the conditions as prescribed by the Presidential Decree and any person who does the construction, etc. of school facilities under the proviso of
Article 4
(1) shall, when he completes it, obtain approval for using such school facilities from the supervisory authority.
<Amended by Act No. 6210, Jan. 28, 2000>
(2)
When the supervisory authority receives the report under the former part of paragraph (1), it shall perform the inspection of completion and with respect to the school facilities which passed the inspection of completion, it shall notify the results to the heads of the administrative agencies that have jurisdiction over the matters of each subparagraph of
Article 5
and the head of
Si
/
Gun
/
Gu
, and publish such results. The supervisory authority shall, when it grants approval for using school facilities in accordance with the provisions of the latter part of paragraph (1), deliver a letter of approval for using the school facilities and then serve a notice thereof on each of the heads of administrative agencies that have jurisdiction over the matters of each subparagraph of
Article 5
and the head of
Si
/
Gun
/
Gu
, respectively.
<Amended by Act No. 6210, Jan. 28, 2000>
(3)
When the State or local government has completed the school facilities project, it shall notify the matters concerning it to each of the heads of the administrative agencies that have the jurisdiction over the applicable matters of each subparagraph of
Article 5
and the head of
Si
/
Gun
/
Gu
and publish such results:
Provided
, That in case the construction, etc. of school facilities is completed under
Article 4
(1), it shall not require being published.
<Amended by Act No. 6210, Jan. 28, 2000>
(4)
When the supervisory authority publishes the results or delivers a letter of approval for use and then serves a notice thereof under paragraph (2), the school facilities concerned shall be considered to have passed the usability test as referred to in
Article 18 of the Building Act
, and when the State or local government has notified the matters concerning the completion of the school facilities project to the head of
Si
/
Gun
/
Gu
under paragraph (3), the notice shall be considered the one served under the proviso of
Article 25 (3) of the Building Act
.
<Amended by Act No. 6210, Jan. 28, 2000>
(5)
When the head of
Si
/
Gun
/
Gu
has receives the notification under paragraph (2) or (3), he shall record it without delay in the building register or building control register referred to in the Acts and subordinate statutes related to building.
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 14 (Rearrangement of Graves)
(1)
If the supervisory authority deems it necessary for the execution of the school facilities project, (in case the State or local government is the undertaker of the school facilities project, it refers to the project undertaker concerned; hereinafter this Article the same shall apply) it may order the burier, owner or manager of the grave, or the relatives of the buried (hereinafter referred to as the “relatives, etc.”) to change the burial site or remove graves, tombstones, and their accessory facilities (hereinafter as referred to as the “graves, etc.”) within the execution site of the school facilities.
(2)
When the relatives, etc. of the graves, etc. do not conform to the order to change or move the burial site as referred to in paragraph (1), the supervisory authority may execute it by proxy as prescribed by the
Administrative Vicarious Execution Act
.
(3)
In case of paragraph (1), when the relatives, etc. of the graves, etc. are unknown, the supervisory authority shall put a notice, for a given period of time, ordering the change or removal of the graves, etc., and if graves, etc. are not changed or removed within the time period, the supervisory authority may change or remove them.
(4)
The supervisory authority shall pay the person, who has changed or removed the graves, etc. according to the order to change or remove graves, etc. referred to in paragraph (1), for the expenses involved in the action.
(5)
The cost of the execution by proxy as referred to in paragraph (2), the cost of the changing or removal of the burial site as referred to in paragraph (3), and the expenses referred to in paragraph (4) shall be born by the project undertaker.
(6)
The project undertaker shall include the plans for rearrangement of the graves, etc. in the execution plan.
[This Article Added by Act No. 3740, Aug. 2, 1984]
법령보기 화면
Article 15 (Delegation of Authority)
(1)
The Minister of Education may delegate part of his authority referred to in this Act to the superintendent of the board of education as prescribed by the Presidential Decree.
(2)
Deleted.
<by Act No. 6210, Jan. 28, 2000>
(3)
The superintendent of the board of education may delegate part of his authority referred to in this Act to the educational superintendent as prescribed by the Presidential Decree.
[This Article Wholly Amended by Act No. 4881, Jan. 5, 1995]
법령보기 화면
Article 16 Deleted.<by Act No. 6210, Jan. 28, 2000>
ADDENDA
(1)
(Enforcement Date) This Act shall enter into force three months after its promulgation.
(2)
(Special Cases for Application of
Urban Planning Act
to Existing Schools) Among the facilities of elementary, middle, high schools, and special schools that have been established under the
Education Act
before the enforcement of this Act, the school facilities established without obtaining the decision for urban planning referred to in
Article 12 of the Urban Planning Act
, the permission for urban planning project execution by any urban planning project undertaker who is not an administrative agency referred to in
Article 24
of the same Act, and the authorization of urban planning project execution plan referred to in
Article 25
of the same Act and conforming to the standards determined by the Presidential Decree shall be considered the facilities established with the decision for urban planning, the permission for urban planning project execution on and the authorization for urban planning project execution on plan referred to in
Articles 12
,
24
and
25
, respectively, of the
Urban Planning Act
:
Provided
, That if the land register for the facilities is uncertain, it shall be established by the public notification of the land register referred to in
Article 13 of the Urban Planning Act
. In this case, a copy of the land registration map may substitute for the application draft for the public notification of land register.
ADDENDA<Act No. 3740, Aug. 2, 1984>
(1)
(Enforcement Date) This Act shall enter into force 30 days after its promulgation.
(2)
(Transitional Measures) The public notification of the execution plan for any school facilities project and approval of that execution on plan that has been approved or passed through consultation under the previous provisions before the enforcement of this Act shall be regarded as the public notice of the execution plan for school facilities project and approval of that execution plan referred to in the amended provisions of
Article 10
. under the proviso of Article 25 (3) of the
Building Act
.
Article 3
Omitted.
ADDENDA<Act No. 5069, Dec. 29, 1995>
Article 1 (Enforcement Date)
This Act shall enter into force on March 1, 1996.
Articles 2 through 4 Omitted.
ADDENDA<Act No. 5453, Dec. 13, 1997>
Article 1 (Enforcement Date)
This Act shall enter into force on January 1, 1998. (Proviso Omitted.)
Article 2 Omitted.
ADDENDUM<Act No. 5454, Dec. 13, 1997>
This Act shall enter into force on January 1, 1998. (Proviso Omitted.)
ADDENDA<Act No. 5893, Feb. 8, 1999>
Article 1 (Enforcement Date)
This Act shall enter into force six months after the date of its promulgation.
Articles 2 through 6 Omitted.
ADDENDUM<Act No. 6210, Jan. 28, 2000>
This Act shall enter into force on the date of its promulgation.
Last updated : 2009-07-26