FAIR TRANSACTIONS IN SUBCONTRACTING ACT

3191 · 2000-07-22

FAIR TRANSACTIONS IN SUBCONTRACTING ACT  Act No. 6198, Jan. 21, 2000   Act No. 3779, Dec. 31, 1984 Amended by Act No. 4198, Jan. 13, 1990 Act No. 4419, Dec. 14, 1991 Act No. 4514, Dec. 8, 1992 Act No. 4898, Jan. 5, 1995 Act No. 4860, Jan. 5, 1995 Act No. 5234, Dec. 30, 1996 Act No. 5386, Aug. 28, 1997 Act No. 5454, Dec. 13, 1997 Act No. 5507, Jan. 13, 1998 Act No. 5816, Feb. 5, 1999 Act No. 5756, Feb. 5, 1999 Act No. 6198, Jan. 21, 2000 법령보기 화면  Article 1 (Purpose) The purpose of this Act is to contribute to the sound development of the national economy by establishing a fair order for subcontracting so that the a prime contractor and a subcontractor may attain a complementary and harmonious growth on an equal status. 법령보기 화면  Article 2 (Definitions) (1) For the purpose of this Act, the term “subcontract” means an act that a prime contractor entrusts a subcontractor with the manufacture (including the processing; hereinafter the same shall apply), repair or construction, or a contractor re-entrusts a subcontractor with the manufacture, repair or construction which the prime contractor is entrusted with by another contractor, and the subcontractor who is entrusted therewith (hereinafter referred to as the “entrustment with the manufacture, etc.”) manufactures, repairs or executes what has been entrusted (hereinafter referred to as the “object”) and supplies or delivers it (hereinafter referred to as “supply of object”) to the prime contractor, and receives the price thereof (hereinafter referred to as the “subcontract price”). (2) For the purpose of this Act, the term “prime contractor” means any persons who fall under one of the following subparagraphs: <Amended by Act No. 4419, Dec. 14, 1991; Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996; Act No. 5816, Feb. 5, 1999> 1. An entrepreneur other than the small and medium enterprise owner (the persons referred to in the provisions of Article 2 (1) of the Framework Act on Small and Medium Enterprises , including the small and medium enterprise cooperatives prescribed by the Small and Medium Enterprise Cooperatives Act ; hereinafter the same shall apply), who entrusts a small and medium enterprise owner with the manufacture, etc.; 2. A small and medium enterprise owner whose annual sales in the immediately preceding business year (in case of a trade which is subject to the appraisal of capacity for executing works under the related Acts, it refers to the total amount thereof in the year concerned, and in the absence of the annual sales or the appraisal of capacity for executing works, it refers to the total assets; hereinafter in this subparagraph the same shall apply), or whose number of ordinary employees exceeds twice that of other small and medium enterprise owners who are entrusted with the manufacture, etc., and who entrusts other small and medium enterprise owner with the manufacture, etc., except the small and medium enterprise owner whose annual sales are equal to the amount prescribed by the Presidential Decree; and 3. and 4. Deleted. <by Act No. 4860, Jan. 5, 1995> (3) For the purpose of this Act, the term “subcontractor” means a small and medium enterprise owner who is entrusted with the manufacture, etc. by the prime contractor as referred to in each subparagraph of paragraph (2) of this Article. <Amended by Act No. 4860, Jan. 5, 1995> (4) If an entrepreneur entrusts an affiliated company as prescribed in subparagraph 3 of Article 2 of the Monopoly Regulation and Fair Trade Act with the manufacture, etc., and the affiliated company re-entrusts a third person with the whole or part of the entrusted manufacture, repair or work execution, and even though the affiliated company does not fall under any of the subparagraphs of paragraph (2), if the third person falls under the provisons of paragraph (3) on the assumption that he is entrusted with the manufacture, etc. directly by the entrepreneur who entrusts it to the affiliated company, the affiliated company and the third person shall be considered as the prime contractor and the subcontractor as prescribed by this Act, respectively. <Amended by Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> (5) If a company belonging to a large business conglomerate as prescribed in Article 9 (1) of the Monopoly Regulation and Fair Trade Act entrusts or is entrusted with the manufacture, etc., it shall be governed by the provisions which fall under each of the following subparagraphs: <Newly Inserted by Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> 1. Even though the company which entrusts the manufacture, etc. does not fall under any subparagraph of this Article 2 (2), it shall be considered as the prime contractor as prescribed by this Act; and 2. Even though the company which is entrusted with the manufacture, etc., falls under paragraph (3) of this Article, it shall not be considered as the subcontractor prescribed by this Act. (6) For the purpose of this Act, the term “entrustment with the manufacture” means an entrepreneur engaged in such business for profit which falls under one of the following subparagraphs, entrusts another entrepreneur with the manufacture of goods resulting from such business. In this case, the scope of goods resulting from such business shall be prescribed and a public notice thereof shall be made by the Fair Trade Commission: <Amended by Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996; Act No. 6198, Jan. 21, 2000> 1. Manufacture of goods (including the software business as prescribed in subparagraph 3 of Article 2 of the Software Industry Development Act, the engineering activities as prescribed in Article 2 of the Engineering Technology Promotion Act , and the designs as prescribed in subparagraph 3 of Article 2 of the Certified Architects Act ; hereinafter the same shall apply); 2. Sale of goods; 3. Repair of goods; and 4. Construction. (7) With respect to such goods as specified by the Presidential Decree, despite the provisions of Article 6 , the provisions of the said Article shall apply to only the areas such as Special Metropolitan City and Metropolitan City, etc. prescribed by the Presidential Decree. <Newly Inserted by Act No. 5,234, Dec. 30, 1996> (8) For the purpose of this Act, the term “entrustment with the repair” means an entrepreneur engaged in a business for profit to repair goods according to the customer’s order, or in a business for profit to repair the goods he is using, entrusts another entrepreneur with the whole or part of such act of repairing. (9) For the purpose of this Act, the term “entrustment with the construction” means an entrepreneur falling under any of the following subparagraphs (hereinafter referred to as the “constructor”) entrusts another constructor with the whole or part of any construction work resulting from his business, and that a constructor entrusts another entrepreneur with the construction work as prescribed by the Presidential Decree: <Amended by Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996; Act No. 5386, Aug. 28, 1997; Act No. 5454, Dec. 13, 1997; Act No. 5756, Feb. 5, 1999> 1. Constructor as prescribed in subparagraph 5 of Article 2 of the Framework Act on the Construction Industry ; 2. A construction work businessman as prescribed in subparagraph 3 of Article 2 of the Electrical Construction Business Act ; 3. A construction work businessman as prescribed in subparagraph 4 of Article 2 of the Information and Communication Work Business Act ; 4. A person who registers a fire protection systems construction business under Article 52 (1) of the Fire Service Act; and 5. Other entrepreneurs as prescribed by the Presidential Decree. (10) For the purpose of this Act, the term “ordering person” means a person who contracts the manufacture, repair or execution of works to a prime contractor: Provided , That in case of a re-subcontract, it means a prime contractor. <Newly Inserted by Act No. 5816, Feb. 5, 1999> 법령보기 화면  Article 3 (Delivery of Writing and Keeping of Documents) (1) If a prime contractor entrusts a subcontractor with the manufacture, etc., he shall deliver a written document in which the prescribed matters are specified to the subcontractor in advance (in case of the entrustment with the manufacture, before a subcontractor commences any work for the supply of objects; in case of the entrustment with the repair, before a subcontractor commences any act of the repair for which a contract is concluded; in case of the entrustment with the construction, before a subcontractor commences any contracted construction work) unless there exists any justifiable reason. <Amended by Act No. 5816, Feb. 5, 1999> (2) The document as referred to in paragraph (1) of this Article shall include the subcontract price and the matters as prescribed by the Presidential Decree, such as the method of payment, etc., and the prime contractor and the subcontractor shall put their signatures and affix their seals on it. (3) The prime contractor and the subcontractor shall keep the documents concerning the subcontract under the provisions of the Presidential Decree. 법령보기 화면  Article 3-2 (Preparation and Use of Standard Subcontract Form) The Fair Trade Commission may recommend the preparation and use of the standard subcontract form to the entrepreneur or entrepreneurs organization to which this Act applies. [This Article Newly Inserted by Act No. 4860, Jan. 5, 1995] 법령보기 화면  Article 4 (Prohibition of Determining Unreasonable Subcontract Price) (1) In the event that a prime contractor entrusts a subcontractor with the manufacture, etc., he shall not compel the subcontractor to determine the subcontract price at a remarkably lower level than the price paid ordinarily for the same or similar manufacture, etc. of the object by using unlawful methods (hereinafter referred to as the “determination of the unreasonable subcontract price”), or to accept such subcontract. (2) If the act of the prime contractor falls under one of the following subparagraphs it shall be considered as the determination of the unreasonable subcontract price as referred to in paragraph (1) of this Article: 1. An act determining the subcontract price by reducing the unit price at a uniform rate, without any justifiable reasons; 2. An act determining the subcontract price by deducting any amount after allotting unilaterally such amount, regardless of the pretext, such as a request for cooperation, etc.; 3. An act determining the subcontract price by discriminating against any specified subcontractor without any justifiable reasons; 4. An act determining the subcontract price by causing the subcontractor to make an error regarding the terms and conditions of the transaction such as the ordered quantity, etc., or by deceiving the subcontractor in such a way as to show him the quotations of another entrepreneur or false quotations to take advantage of it; and 5. An act of the prime contractor determining unilaterally the subcontract price at an unreasonably low unit price. 법령보기 화면  Article 5 (Prohibition of Forced Purchase of Goods, etc.) If the prime contractor entrusts the subcontractor with the manufacture, etc., he shall not compel a subcontractor to purchase or use any goods, equipment, etc. designated by him, unless it is required to maintain or improve the quality of the object, or there is any justifiable reason. 법령보기 화면  Article 6 (Payment of Advance) (1) If the prime contractor who has entrusted a subcontractor with the manufacture, etc., receives any advance from the ordering person, he shall pay the advance to the subcontractor to enable him to undertake the manufacture, repair or construction work, in accordance with the contents and ratio of the advance, within fifteen days after he has received it (if he receives it before he entrusts the manufacture, etc., the day on which he entrusts the manufacture, etc.). (2) If the prime contractor pays the advance received from the ordering person beyond the time limit as referred to in paragraph (1) of this Article, he shall pay the interest calculated by the interest rate prescribed and notified by the Fair Trade Commission. <Newly Inserted by Act No. 4514, Dec. 8, 1992; Act No. 5507, Jan. 13, 1998> (3) The provisions of Article 13 (6) and (8) (Payments, etc. of Subcontract Prices) shall apply mutatis mutandis to discount charges and rates for the bill if such bill is paid as an advance under paragraph (1) of this Article. In this case, the wording “sixty days from the date when such objects have been received” referred to in Article 13 (1) shall be considered as the wording “fifteen days from the date when the prime contractor has received the advance payments from the ordering person.” <Newly Inserted by Act No. 5234, Dec. 30, 1996; Act No. 5816, Feb. 5, 1999> 법령보기 화면  Article 7 (Opening of Local Letter of Credit) If the prime contractor entrusts the subcontractor with the manufacture of goods to be exported, he shall open a local letter of credit in favor of the subcontractor, within fifteen days from the date of the entrustment, unless there is any justifiable reason: Provided , That in the case of an export under a letter of credit, if the prime contractor entrusts the manufacture before he receives the original letter of credit, he shall open the local letter of credit within fifteen days after he has received the original letter of credit. <Amended by Act No. 4514, Dec. 8, 1992> 법령보기 화면  Article 8 (Prohibition of Unreasonable Refusal to Receive Goods and Delivery of Receipt) (1) No prime contractor shall cancel or change arbitrarily any entrustment of the manufacture, etc., or refuse to receive or postpone the delivery of the object, unless there is any reason attributable to the subcontractor. (2) If the object is supplied, the prime contractor shall immediately [immediately after the completion of inspection if a local letter of credit has been opened pursuant to the provisions of Article 7 (Opening of Local Letter of Credit)] deliver a certificate of receipt to the subcontractor, even before an inspection of the object is conducted: Provided , That in the case of an entrustment of construction, he shall take over the object immediately after the inspection has been finished. <Amended by Act No. 5234, Dec. 30, 1996> (3) For the purpose of paragraph (1) of this Article, the term “receipt” means that the prime contractor receives the object supplied by the subcontractor, and places it under his control: Provided , That if it is difficult to move the object to another place, the time when the inspection commences shall be considered as the time of receipt. 법령보기 화면  Article 9 (Criteria, Method and Time of Inspection) (1) The criteria and method of the inspection of the object supplied or delivered by the subcontractor shall be determined after the contractor consults with the subcontractor, but it shall be objective, impartial and reasonable. (2) Unless there is any justifiable reason, the contractor shall notify in writing the subcontractor of the result of the examination of goods within ten days from the date when he has received such goods (in the case of manufacturing services, it includes the date when the portion of manufacturing work performed has been notified, and in the case of construction services, it includes the date when the subcontractor has notified the completion of construction work, or the portion of construction work completed). In the absence of such notification within the prescribed period, the goods shall be deemed to have passed the inspection. <Amended by Act No. 5234, Dec. 30, 1996> 법령보기 화면  Article 10 (Prohibition of Unreasonable Return) (1) When the prime contractor has received or taken over the object from the subcontractor, he shall not return it to the subcontractor, unless the need to return the object is attributable to the subcontractor (hereinafter referred to as the “unreasonable return”). (2) The acts of the prime contractor which fall under any of the following subparagraphs shall be considered as the unreasonable return under paragraph (1) of this Article: 1. An act of returning the object by reason of a cancellation of the order from the other party to the transaction, or any change in the economic situation, etc.; 2. An act of returning the object by determining vaguely the criteria and method of inspection, and thereby judging the object as one which fails to pass the inspection; 3. An act of returning the object, although it is judged as inferior due to the inferior quality of the raw materials supplied by the prime contractor; and 4. An act of returning the object by reason of a delay of supply, although it is caused by a delay in the supply of raw materials by the prime contractor. 법령보기 화면  Article 11 (Prohibition of Unreasonable Reduction of Price) (1) The prime contractor shall not reduce unreasonably the subcontract price determined at the time of the entrustment of the manufacture, etc. (hereinafter referred to as the “unreasonable reduction of the price”), unless there is any reason attributable to the subcontractor. (2) The acts of the contractor which fall under any of the following subparagraphs shall be considered as an unreasonable reduction of price under paragraph (1) of this Article: 1. An act of reducing the subcontract price by unjustifiable reasons, such as a request for cooperation, cancellation of the order by the other party to the transaction, a change in the economic situation, etc., after making the entrustment without specifying the conditions on which the subcontract price will be reduced at the time of the entrustment; 2. An act of reducing the subcontract price by applying unilaterally and retroactively the unit price reduced by an agreement with the subcontractor on the reduction thereof to any portion entrusted prior to such agreement; 3. An act of reducing excessively the subcontract price for the reason that the subcontract price is paid in cash or prior to the due date of payment; 4. An act of reducing unilaterally the subcontract price for the reason of any insignificant fault of the subcontractor, which does not have any substantial effect on the occurrence of damage against the prime contractor; and 5. An act of deducting any amount more than the proper purchase price or the price of use from the subcontract price, if the prime contractor has the subcontractor purchase from him the goods, etc. required for the manufacture, repair or execution of the object, or use his equipment, etc.. (3) If the prime contractor pays the price reduced unfairly in violation of paragraph (1) of this Article more than sixty days after receipt of the goods, the prime contractor shall pay interest accrued for the period beyond sixty days on the price in accordance with interest rates prescribed and notified by the Fair Trade Commission for such overdue days. <Amended by Act No. 5234, Dec. 30, 1996; Act No. 5507, Jan. 13, 1998> 법령보기 화면  Article 12 (Prohibition of Claim for Unreasonable Settlement of Goods Purchase Price, etc.) If the prime contractor asks the subcontractor to purchase from him the goods, etc. required for the manufacture, repair or execution of the object, or to use his equipment, etc., he shall not ask the subcontractor to pay the whole or part of the price of purchase or use prior to the date of payment of the subcontract price for the object, or pay it under remarkably unfavorable conditions compared with the conditions under which he purchases or uses it, or supplies it to a third person, without any justifiable reasons. [This Article Wholly Amended by Act No. 4860, Jan. 5, 1995] 법령보기 화면  Article 13 (Payment, etc. of Subcontract Price) (1) If the prime contractor entrusts the subcontractor with the manufacture, etc., he shall pay the subcontract price by the date of payment determined as soon as possible within the limit of sixty days from the date of receiving the object (in the case of the entrustment of construction, it refers to the date of taking over the object, and if the prime contractor and the subcontractor determine the date of issue of the tax invoice once or more each month, because goods are supplied frequently, it refers to such determined date; hereinafter the same shall apply), except the cases which fall under any of the following subparagraphs: <Amended by Act No. 4514, Dec. 8, 1992> 1. Where it is deemed that the prime contractor and the subcontractor have determined the date of payment on an equal status; and 2. Where the date of payment is deemed reasonable in light of the characteristics of the business and the economic conditions. (2) If the payment date of the subcontract price is not determined, the date of receiving the object shall be considered as the payment date of subcontract price, and if the date of payment is determined in excess of sixty days from the receipt date of the object (excluding the case falling under the proviso of paragraph (1) of this Article), the sixtieth day from the receipt date of object shall be considered as the payment date of the subcontract price, respectively. (3) In the case of the entrustment of manufacture, etc. if the prime contractor has received the completion money from the ordering person, he shall pay to the subcontractor the subcontract price, and if he has received the price for the already completed portion, he shall pay the amount equivalent to the portion executed by the subcontractor within fifteen days after he has received it (if the payment date of subcontract price becomes due earlier, the date of payment). <Amended by Act No. 5234, Dec. 30, 1996; Act No. 5816, Feb. 5, 1999> (4) In paying a subcontract price to a subcontractor, a prime contractor shall not pay less than the proportion of cash which an ordering person gives in connection with the entrustment with the manufacture concerned. <Newly Inserted by Act No. 5816, Feb. 5, 1999> (5) If a prime contractor pays a subcontract price by a bill, he shall not deliver a bill exceeding a period of payment (from the issuance date till the due date) of another bill which an ordering person delivers to him in connection with the entrustment with the manufacture concerned. <Newly Inserted by Act No. 5816, Feb. 5, 1999> (6) If the prime contractor pays the subcontract price by a bill, it shall be the one which can be discounted at any financial institution established under the legal provisions and the discount charges for the period from the delivery date of the bill to the due date thereof shall be paid to the subcontractor on the day on which the bill is delivered: Provided , That if the bill is delivered within sixty days after the object is received (if the date of payment is determined under the proviso of paragraph (1) of this Article, it refers to the due date of payment, and if any money for completion or already completed portion is paid by the order person, it refers to the date as referred to in paragraph (3) of this Article; hereinafter in this Article the same shall apply), the discount charges for the period from the date on which sixty days have passed since the date of receiving the object, to the due date of the bill shall be paid to the subcontractor within sixty days from the date of receiving the object. <Amended by Act No. 4860, Jan. 5, 1995> (7) If the prime contractor pays the subcontract price after the expiration of sixty days from the date of receiving the object, he shall pay the interest calculated by interest rates determined and notified by the Fair Trade Commission for such overdue days. <Amended by Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996; Act No. 5507, Jan. 13, 1998> (8) The discount rate applicable under paragraph (6) of this Article shall be determined and announced publicly by the Fair Trade Commission taking into consideration the commercial bill discount rates applicable by respective city banks. <Newly Inserted by Act No. 4514, Dec. 8, 1992; Act No. 5816, Feb. 5, 1999> 법령보기 화면  Article 13-2 (Guarantee for Performance of Construction Subcontracts and for Payment of Price) (1) In the case of entrustment with the construction, the prime contractor shall provide guarantees for the payment of the price for construction work in accordance with the categories which fall under each of the following subparagraphs, while the subcontractor shall provide the performance bond equivalent to ten percent of the agreed price of such construction work: Provided , That if the financial status of the prime contractor or the size of construction work does not require such guarantees, or if such guarantees are deemed inappropriate under the provisions of the Presidential Decree, this shall not apply: 1. The amount of the price calculated by the deduction of an advance payment from the contract amount in the case of the construction work for the period not exceeding four months; 2. The amount of the price calculated by the following computation formula in the case of construction work for a period of more than four months, during which the period of installment for the completed portion of the work is not more than two months: 3. The amount of the price calculated by the following computation formula in the case of construction work for a period of more than four months, during which the period of installment for the completed portion of the work is more than the two months: (Amount of Guarantee)={(Subcontract amount-Agreed advance payment) ÷(Period of Construction Work(Number of months)}×(period of installment for the completed portion of the Work(Number of months))×2 (2) Such guarantees or bonds as between the prime contractor and subcontractor in accordance with paragraph (1) of this Article shall be delivered in cash (including cashier’s check issued by post offices, or by banking institutions under the Banking Act ) or by the guarantee certificates issued by the institutions which fall under any of the following subparagraphs: <Amended by Act No. 5454, Dec. 13, 1997> 1. Each mutual-aid association under the Framework Act on the Construction Industry ; 2. Insurer operators under the Insurance Business Act ; 3. Credit Guarantee Fund under the Credit Guarantee Fund Act ; 4. Banking institutions under the Banking Act ; or 5. Other guarantee institutions prescribed by the Presidential Decree. (3) Where the prime contractor delivers the guarantee certificates in accordance with paragraph (2) of this Article, the prime contractor may deliver a guarantee certificate evidencing a guarantee for the payment of the price for all construction works which have been offered for construction services for the period of construction work, or for one fiscal year. (4) Apart from such matters specified in paragraphs (1) through (3), the matters necessary for the performance bond for the subcontracts and guarantee of the price payments of subcontracts shall be prescribed by the Presidential Decree. [This Article Newly Inserted by Act No. 5234, Dec. 30, 1996] 법령보기 화면  Article 14 (Direct Payment of Subcontract Price) (1) If there occurs any reason as prescribed in the Presidential Decree, such as the obvious reason why a prime contractor is unable to pay a subcontract price on account of his bankruptcy or dishonor, an ordering person shall directly pay a subcontractor a subcontract price equivalent to a price of manufacture, repair or execution of works of the said subcontractor. (2) If there occurs any reason as prescribed in paragraph (1), a price payment obligation of an ordering person to a prime contractor and a subcontract price payment obligation of a prime contractor to a subcontractor shall be deemed to be extinguished within the limit of a price which is directly paid under paragraph (1). (3) If a prime contractor requires the suspension of direct payment of a subcontract price concerned with documents which are able to prove the fact that a subcontractor delays the payment of wages or prices of materials in connection with a subcontract concerned, an ordering person may not pay the said subcontract price directly notwithstanding the provisions of paragraph (1). [This Article Wholly Amended by Act No. 5816, Feb. 5, 1999] 법령보기 화면  Article 15 (Payment of Refund of Customs Duties) (1) If the prime contractor entrusts the subcontractor with the manufacture of goods to be exported and if he has the customs duties refunded under the Act on Special Cases concerning the Refundment of Customs Duties, etc. Levied on Raw Materials for Export , he shall pay the refunded amount to the subcontractor in accordance with contents of the received refund within fifteen days after he has received it. (2) Notwithstanding the provisions of paragraph (1) of this Article, the due date for the payment of the amount equivalent to the refund of customs duties, etc. to the subcontractor may not exceed sixty days from the date of receiving the object, unless there is any reason attributable to the subcontractor. (3) If the prime contractor pays the amount equivalent to the refund of the customs duties, etc. beyond the due date as referred to in paragraphs (1) and (2) of this Article, he shall pay interest calculated by the interest rate prescribed and notified by the Fair Trade Commission for such overdue days. <Newly Inserted by Act No. 4514, Dec. 8, 1992; Act No. 5507, Jan. 13, 1998> 법령보기 화면  Article 16 (Adjustment of Subcontract Price Due to Change of Design) (1) If the prime contractor receives any additional amount from the ordering person due to any change of the design, the economic situation, etc., after entrusting the manufacture, etc., if any additional expenses are required for completing the object for the same reason, he shall increase the subcontract price in proportion to the additional amount, and if he has the amount reduced by the ordering person, he may reduce the subcontract price in proportion to it. (2) The increase or decrease in the subcontract price as referred to in paragraph (1) of this Article shall be made within thirty days after the contractor has the price increased or decreased by the ordering person. <Newly Inserted by Act No. 4860, Jan. 5, 1995> (3) The provisions of Article 13 (7) (Payments, etc. of Subcontract Price) shall apply mutatis mutandis to interests accrued if the prime contractor pays the subcontract price in excess of fifteen days after receiving the additional amount under paragraph (1) above while the provisions of paragraphs (6) and (8) of the said Article shall apply mutatis mutandis to the payment of discount charges or rates if the additional amount has been paid by a bill or other negotiable instruments respectively. <Newly Inserted by Act No. 5234, Dec. 30, 1996; Act No. 5816, Feb. 5, 1999> 법령보기 화면  Article 17 (Prohibition of Unreasonable Payment in Accord and Satisfaction) The prime contractor shall not pay the subcontract price with goods contrary to the intention of the subcontractor. 법령보기 화면  Article 18 (Prohibition of Unreasonable Intervention in Management) The prime contractor shall not intervene in the management of the subcontractor by means of regulating the quantity of the subcontract. 법령보기 화면  Article 19 (Prohibition of Retaliatory Measures) The prime contractor shall not do any act limiting the opportunity of the subcontractor to receive the order, suspending the transactions with him, or giving him any other disadvantageous treatment for the reason that he has informed the related agency, etc. of any violation of this Act by the prime contractor. 법령보기 화면  Article 20 (Prohibition of Evasion of this Act) The prime contractor shall not do any act evading or circumventing substantially the application of this Act in connection with the subcontract. 법령보기 화면  Article 21 (Matters to be Observed by Subcontractor) (1) The subcontractor shall, upon being entrusted with the manufacture, etc. by the prime contractor, fulfill the contents of the entrustment in faith and trust. (2) No subcontractor shall cooperate with the prime contractor in any offense against this Act. (3) The subcontractor shall, upon making a report as prescribed by this Act, present promptly documentary evidence, etc. to the Fair Trade Commission. <Amended by Act No. 4198, Jan. 13, 1990> 법령보기 화면  Article 22 (Report, etc. on Offense) (1) If it is deemed that there exists any fact contrary to this Act, any person may report it to the Fair Trade Commission. <Amended by Act No. 4198, Jan. 13, 1990> (2) If there is a report as referred to in paragraph (1) of this Article, or it is deemed that there exists any fact contrary to this Act, the Fair Trade Commission may conduct any necessary investigation. <Amended by Act No. 4198, Jan. 13, 1990> (3) If the Fair Trade Commission receives a report from the subcontractor of any offense of the prime contractor and notifies it to the prime contractor, the demand as prescribed in Article 174 of the Civil Act shall be considered to have been made, unless the reported case is dismissed, rejected or withdrawn. <Newly Inserted by Act No. 4514, Dec. 8, 1992> 법령보기 화면  Article 23 (Limitation on Transaction Subject to Investigation) A subcontractor whom the Fair Trade Commission begins to investigate under Article 22 (Reports, etc as to Offences), paragraph (2) shall be limited to those transactions within three years from the day on which the transaction is closed: Provided , That in a case where a subcontractor is reported within three years from the day on which the transaction is closed, the investigation may be conducted even though three years have passed from the day on which the transaction is closed. <Amended by Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> [This Article Wholly Amended by Act No. 4514, Dec. 8, 1992] 법령보기 화면  Article 24 (Subcontract Dispute Mediation Council) (1) The entrepreneur organization as prescribed by the Presidential Decree shall establish the Subcontract Dispute Mediation Council (hereinafter referred to as the “Council”). (2) The Council shall confirm the fact with respect to any dispute over a subcontract between a prime contractor and subcontractor, and mediate it, upon the request of the Fair Trade Commission. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 5234, Dec. 30, 1996> (3) When the dispute is mediated, the Council shall report without delay the result to the Fair Trade Commission, and if not, the reasons for the failure to mediate it. <Amended by Act No. 4198, Jan. 13, 1990> (4) Matters necessary for the composition, operation, etc. of the Council, shall be prescribed by the Presidential Decree. 법령보기 화면  Article 24-2 (Advisors) (1) The Fair Trade Commission may designate advisors, if it is deemed necessary for the performance of functions and duties arising out of subcontracts under this Act. (2) As to the designation of advisors pursuant to paragraph (1) of this Article, other necessary matters shall be prescribed by the Presidential Decree. [This Article Newly Inserted by Act No. 5234, Dec. 30, 1996] 법령보기 화면  Article 25 (Corrective Measures) (1) The Fair Trade Commission may recommend or order an ordering person and a prime contractor who have violated the provisions of Articles 3 (Delivery of Writing and Keeping of Documents) and 4 (Prohibition of Unfair Determination of Subcontract Price) through 20 (Prohibition of Evasion of this Act) to pay a subcontract price, to discontinue such violations, and to take other measures necessary for correcting said violations. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996; Act No. 5816, Feb. 5, 1999> (2) If the mediation of the Council is made under Article 24 (the Subcontract Dispute Conciliation Council) (2), it shall be deemed that the Fair Trade Commission has taken measures necessary for the correction under paragraph (1) in such a manner as the Council mediated the dispute, unless there is any special reason. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 5234, Dec. 30, 1996> (3) Deleted. <by Act No. 4198, Jan. 13, 1990> (4) The Fair Trade Commission may, upon issuing a correction order (excluding the correction order as referred to in paragraph (2); hereinafter in this paragraph the same shall apply) under paragraph (1), order the prime contractor who has received the order, to announce publically the fact that he has received such an order. <Amended by Act No. 4860, Jan. 5, 1995> 법령보기 화면  Article 25-2 (Deposit) If the subcontractor fails to have the obligation performed or is unable to have it performed, the prime contractor who has received the correction order as prescribed in Article 25 (Corrective Measures) (1) or (2) may be exempted from the obligation to perform the corrective measures by depositing the object of the performance in favor of the subcontractor. This shall also apply if it is impossible for the prime contractor without his fault to contact the subcontractor if the subcontractor’s address of whereabouts is unknown. [This Article Newly Inserted by Act No. 4514, Dec. 8, 1992] 법령보기 화면  Article 25-3 (Penalty) (1) The Fair Trade Commission may impose upon an ordering person, a prime contractor or a subcontractor falling under any of the following subparagraphs a penalty not exceeding the amount double the subcontract price for the entrustment of the manufacture, etc. by the prime contractor: <Amended by Act No. 5816, Feb. 5, 1999> 1. A prime contractor who fails to deliver a written document or delivers a false written document in violation of Article 3 (1) and (2) (Delivery of Writing and Keeping of Documents); 2. A person who fails to keep the documents in violation of Article 3 (3) (Delivery of Writing and Keeping of Documents), or the contractor or the subcontractor who prepares or delivers the documents of a subcontract in a fraudulent way; 3. A prime contractor who violates Articles 4 (Prohibition of Unfair Determination of Subcontract Price) through 13-2 (Performance Bond of Subcontracts and Payment Guarantee of Price); 4. An ordering person who violates Article 14 (Direct Payment of Subcontract Price); or 5. A prime contractor who violates Articles 15 (Payments of Refunded Customs Duties, etc.) through 20 (Prohibition of Evasion of this Act). (2) The provisions of Articles 55-3 (Imposition of Penalty) through 55-5 (Collection of Penalty and Penalty in Arrears) under the Monopoly Regulation and Fair Trade Act shall apply mutatis mutandis to the penalty under paragraph (1) of this Article [This Article Newly Inserted by Act No. 5234, Dec. 30, 1996] 법령보기 화면  Article 26 (Cooperation by Head of Administrative Agency Concerned) (1) If it is deemed necessary for enforcing this Act, the Fair Trade Commission may hear the opinion of the head of the administrative agency concerned or request him to provide the support of personnel to conduct an investigation and other necessary cooperation. <Amended by Act No. 4198, Jan. 13, 1990> (2) The Fair Trade Commission may request the head of the administrative agency concerned to limit the eligibility of persons participating in any tender, to suspend the business as prescribed in of Article 82 (1) 6 of the Framework Act on the Construction Industry and to take other measures necessary for the fairness of a subcontract with regard to any prime contractor or subcontractor who violates habitually the provisions of this Act. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 4860, Jan. 5, 1995; Act No. 5454, Dec. 13, 1997> 법령보기 화면  Article 27 (Mutatis Mutandis Application of Monopoly Regulation and Fair Trade Act) (1) The provisions of Articles 42 (Proceedings and Quorum of Meeting) through 45 (Signature and Use of Seals by Members) and 52 (Opportunity of Hearings) of the Monopoly Regulation and Fair Trade Act shall be applicable mutatis mutandis to the deliberation and decision of the Fair Trade Commission under this Act while Articles 53 (Submission of Complaints) through 55-2 (Procedures for Handling Cases, etc) of the said Act shall be apply mutatis mutandis to the exclusive jurisdiction over any submission of complaints, institution of a lawsuit, or litigation by appeal against any disposition of the Fair Trade Commission. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> (2) The provisions of Articles 50 (Investigation, Hearing of Opinion, etc Unlawful Practices) and 51 (Recommendation for Correction of Unlawful Practices) of the Monopoly Regulation and Fair Trade Act shall be applicable mutatis mutandis to any investigation, hearing of opinion, recommendation for correction, etc. of the Fair Trade Commission against any violations of this Act. <Amended by Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> (3) The provisions of Article 62 (Obligation of Confidentiality) of the Monopoly Regulation and Fair Trade Act shall be applicable mutatis mutandis to any member of the Fair Trade Commission and public official who performs or used to perform the duties as prescribed by this Act, or any person who is or was in charge of the affairs concerning the conciliation of any dispute over a subcontract for the Subcontract Dispute Mediation Council. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> 법령보기 화면  Article 28 (Relation with Monopoly Regulation and Fair Trade Act) The provisions of Article 23 (1) 4 (Prohibition of Unfair Trade Practices) of the Monopoly Regulation and Fair Trade Act shall not be applicable to the matters concerning a subcontract to which this Act applies. <Amended by Act No. 4198, Jan. 13, 1990; Act No. 5234, Dec. 30, 1996> 법령보기 화면  Article 29 (Penal Provisions) Any person who violates the provisions of Article 27 ( mutatis mutandis Application of the Monopoly Regulation and Fair Trade Act) (3) shall be punished by imprisonment for not more than two years, or a fine not exceeding two million won. <Amended by Act No. 4514, Dec. 8, 1992; Act No. 5234, Dec. 30, 1996> 법령보기 화면  Article 30 (Penal Provisions) (1) A prime contractor falling under any of the following subparagraphs shall be punished by a fine not exceeding the amount equivalent to double the subcontract price for the manufacture, etc. entrusted to the subcontractor by the prime contractor, etc.: <Amended by Act No. 5234, Dec. 30, 1996> 1. and 2. Deleted; <by Act No. 5234, Dec. 30, 1996> 3. A person who violates the provisions of Articles 4 (Prohibition of Determination of Unfair Subcontract Price) through 13 (Payments, etc of Subcontract Price); and 4. A person who violates the provisions of Articles 15 (Refund of Customs Duties, etc) through 17 (Prohibition of Unfair Accord and Satisfaction). (2) Any person who falls under any of the following subparagraphs shall be punished by a fine not exceeding one hundred and fifty million won: <Amended by Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> 1. A person who violates the provisions of Articles 18 (Prohibition of Unfair Intervention of Management) through 20 (Prohibition of Evasion of this Act); and 2. A person who fails to comply with an order as prescribed in Article 25 (Corrective Measures) (1), (2) or (4). (3) Any person who conducts a false appraisal in violation of the provisions of Article 50, (Investigation, Hearing of Opinion, etc of Offences) (1) 2 of the Monopoly Regulation and Fair Trade Act which is applicable mutatis mutandis under the provisions of Article 27 ( mutatis mutandis Application of the Monopoly Regulation and Fair Trade Act) (2) shall be punished by a fine not exceeding thirty million won. <Newly Inserted by Act No. 4514, Dec. 8, 1992; Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> 법령보기 화면  Article 30-2 (Fine for Negligence) (1) Any person who falls under any of the following subparagraphs shall be punished by a fine for negligence not exceeding thirty million won: <Amended by Act No. 4860, Jan. 5, 1995; Act No. 5234, Dec. 30, 1996> 1. A person who fails to attend without any justifiable reason, in violation of the provisions of Article 50 (Inquiries, Hearings, etc. of Offences) (1) 1 of the Monopoly Regulation and Fair Trade Act , which is applicable mutatis mutandis under Article 27 ( mutatis mutandis Application of the Monopoly Regulation and Fair Trading Act) (2); 2. A person who fails to make a report, or to submit necessary materials or things as prescribed in Article 50 (Investigation, Hearing of Opinion, etc. of Offences) (1) 3 or (3) of the Monopoly Regulation and Fair Trade Act , which is applicable mutatis mutandis under Article 27 ( mutatis mutandis Application of the Monopoly Regulation and Fair Trade Act) (2), or who makes a false report, or submits false materials or things; and 3. A person who refuses, interferes with, or evades, any inspection as prescribed in Article 50 (Investigation, Hearing of Opinion, etc. of Offences) (2) of the Monopoly Regulation and Fair Trade Act , which is applicable mutatis mutandis under Article 27 ( mutatis mutandis Application of the Monopoly Regulation and Fair Trade Act) (2). (2) Any one who fails to comply with the instruction to maintain a good order, thereby violating the provisions of Article 43-2 (Maintenance of Good Order in the court room) of the Monopoly Regulation and Fair Trade Act which are applicable mutatis mutandis under Article 27 ( mutatis mutandis Application of the Monopoly Regulation and Fair Trade Act) (1), shall be punished by a fine for negligence not exceeding one million won. <Newly Inserted by Act No. 5234, Dec. 30, 1996> (3) The fine for negligence as referred to in paragraph (1) of this Article shall be imposed and collected by the Fair Trade Commission under the provisions of the Presidential Decree. <Amended by Act No. 5234, Dec. 30, 1996> (4) Any person who has raised an objection against a disposition of a fine for negligence as referred to in paragraph (2) of this Article may make an objection against the Fair Trade Commission within thirty days after he is informed of such disposition. <Amended by Act No. 5234, Dec. 30, 1996> (5) If a person who is subject to a disposition of a fine for negligence as referred to in paragraph (3) of this Article, makes an objection under paragraph (4) of this Article, the Fair Trade Commission shall notify the competent court thereof without delay, which shall, upon receiving the notification, bring the case of the fine for negligence to a trial under the Non-Contentious Case Litigation Procedure Act . <Amended by Act No. 5234, Dec. 30, 1996> (6) If no objection is made, and no fine for negligence is paid within the period as referred to in paragraph (4) of this Article , it shall be collected according to the examples of a disposition of national tax in arrears. <Amended by Act No. 5234, Dec. 30, 1996> [This Article Newly Inserted by Act No. 4514, Dec. 8, 1992] 법령보기 화면  Article 31 (Joint Penal Provisions) If a representative of a juristic person, or an agent, serviceman or other employee of a juristic person or an individual commits an offense falling under Article 30 (Penal Provisions) in connection with the affairs of the juristic person or the individual, the fine as prescribed in the respective paragraphs of Article 30 shall also be imposed on such juristic person or individual, in addition to the punishment of the offender. <Amended by Act No. 5234, Dec. 30, 1996> 법령보기 화면  Article 32 (Complaint) An indictment against a crime as prescribed in Article 30 may be made only under a complaint of the Fair Trade Commission. <Amended by Act No. 5234, Dec. 30, 1996> [This Article Wholly Amended by Act No. 4514, Dec. 8, 1992] 법령보기 화면  Article 33 (Both to Blame Provisions) If a subcontractor is liable for any offense committed by a prime contractor against this Act, this may be taken into consideration when taking corrective measures, filing the complaint, or applying the penal provisions under this Act. 법령보기 화면  Article 34 (Relation with Other Acts) If the provisions of the Act on the Protection of the Business Sphere of Small and Medium Enterprises and Promotion of Their Cooperation , the Electrical Construction Business Act , the Framework Act on the Construction Industry , and the Information and Communication Work Business Act are contrary to this Act, such provisions shall be governed by this Act. <Amended by Act No. 4898, Jan. 5, 1995; Act No. 5386, Aug. 28, 1997; Act No. 5454, Dec. 13, 1997> 법령보기 화면  Article 35 (Enforcement Decree) Matters necessary for enforcing this Act shall be prescribed by the Presidential Decree. ADDENDUM This Act shall enter into force three months after the date of its promulgation. ADDENDA<Act No. 4198, Jan. 13, 1990> Article 1 (Enforcement Date) This Act shall enter into force on April 1, 1990. Articles 2 through 5 Omitted ADDENDA<Act No. 4419, Dec. 14, 1991> Article 1 (Enforcement Date) This Act shall enter into force on July 1, 1992. (Proviso is Omitted) Articles 2 through 8 Omitted. ADDENDA<Act No. 4514, Dec. 8, 1992> (1) (Enforcement Date) This Act shall enter into force on April 1, 1993. (2) (Transitional Measures) The amended provisions of Articles 6 , 7 , 13 and 15 shall not apply to any subcontract already concluded at the time this Act enters into force. (3) Omitted. ADDENDA<Act No. 4860, Jan. 5, 1995> (1) (Enforcement Date) This Act shall enter into force on April 1, 1995. (2) (Transitional Measures) Notwithstanding the revised provisions of Articles 2 , 13 (4) and 16 (2), any subcontract already concluded at the time this Act enters into force shall be governed by the previous provisions. ADDENDA<Act No. 4898, Jan. 5, 1995> Article 1 (Enforcement Date) This Act shall enter into force on July 1, 1995. Articles 2 through 11 Omitted. ADDENDA<Act No. 5234, Dec. 30, 1996> (1) (Enforcement Date) This Act shall enter into force on April 1, 1997. (2) (Transitional Measures for Subcontracting Transactions under Conclusion of Subcontracts) If a subcontract was already concluded at the time this Act entered into force, the former provisions of this Act shall apply notwithstanding the amended provisions of Articles 13-2 (Guarantee for Performance of Construction Subcontracts and for Payment of Price) and 25-3 (Penalty). ADDENDA<Act No. 5386, Aug. 28, 1997> Article 1 (Enforcement Date) This Act shall enter into force on January 1, 1998. (Proviso Omitted.) Articles 2 through 8 Omitted. ADDENDUM<Act No. 5454, Dec. 13, 1997> This Act shall enter into force on January 1, 1998. (Proviso Omitted.) ADDENDA<Act No. 5507, Jan. 13, 1998> Article 1 (Enforcement Date) This Act shall enter into force on the date of its promulgation. Article 2 Omitted. ADDENDA<Act No. 5756, Feb. 5, 1999> Article 1 (Enforcement Date) This Act shall enter into force six months after the date of its promulgation. (Proviso Omitted.) Articles 2 through 7 Omitted. ADDENDA<Act No. 5816, Feb. 5, 1999> (1) (Enforcement Date) This Act shall enter into force on April 1, 1999. (2) (Transitional Measures concerning Subcontracting Transaction under Conclusion of Subcontract) Notwithstanding the amended provisions of Article 13 , the previous provisions shall apply to a subcontracting transaction for which a subcontract has already been concluded at the time when this Act enters into force. ADDENDA<Act No. 6189, Jan. 21, 2000> Article 1 (Enforcement Date) This Act shall enter into force six months after the date of its promulgation. Articles 2 through 7 Omitted. Last updated : 2009-07-26