Enforcement Rule of the Special Act on the Creation and Fostering of Urban Convergence Special Zones
262107 · 2024-04-25
Article 1 (Purpose)
The purpose of this Rule is to prescribe matters delegated by the Special Act on the Creation and Fostering of Urban Convergence Special Zones and the Enforcement Decree of that Act, and matters necessary for their enforcement.
Article 2 (Applications for Designation of Urban Convergence Special Zones)
An application for designation or modified designation of an urban convergence special zone under Article 8(1) of the Special Act on the Creation and Fostering of Urban Convergence Special Zones (hereinafter referred to as the "Act") and Article 4(1) of the Enforcement Decree of that Act (hereinafter referred to as the "Decree") shall be made using attached Form No. 1.
Article 3 (Simple Structures)
"Simple structures prescribed by Ordinance of the Ministry of Land, Infrastructure and Transport" in Article 8(3)1 of the Decree means the following structures:
1. Plastic greenhouses;
2. Silkworm rearing facilities;
3. Drying facilities for agricultural, forestry, or fishery products, including peppers, leaf tobacco, and laver;
4. Mushroom cultivation facilities;
5. Seed and seedling propagation facilities;
6. Composting facilities;
7. Threshing facilities;
8. Other structures similar to those specified in subparagraphs 1 through 7 that are determined and publicly notified by the Minister of Land, Infrastructure and Transport.
Article 4 (Designation of Project Implementers for Urban Convergence Special Zone Development Projects)
(1) An application for designation or modified designation as a project implementer under Article 14(1) of the Act and the former part of Article 11 of the Decree, excluding its subparagraphs, shall be made using attached Form No. 2.
(2) An application to carry out an urban convergence special zone development project (hereinafter referred to as a "special zone development project") on behalf of another person under Article 12(1) of the Decree shall be made using attached Form No. 3.
(3) "Cases prescribed by Ordinance of the Ministry of Land, Infrastructure and Transport" in Article 14(4)3 of the Act means the following cases:
1. Where the implementer of a special zone development project (hereinafter referred to as a "project implementer") has obtained designation as a project implementer under Article 14(1) of the Act or approval of an implementation plan for a special zone development project (hereinafter referred to as an "implementation plan") under Articles 15(1) and 16(3) of the Act by false or other improper means;
2. Where an application for approval of an implementation plan under Articles 15(1) and 16(3) of the Act is not made within two years from the date of designation as a project implementer;
3. Where the designation as a project implementer or the approval of an implementation plan under Articles 15(1) and 16(3) of the Act is revoked;
4. Where progress in implementing the special zone development project is markedly poor for reasons attributable to the project implementer.
(4) Where the Minister of Land, Infrastructure and Transport designates or changes a project implementer under Article 14(5) of the Act, the Minister shall publicly notify the following matters in the Official Gazette:
1. Type and name of the special zone development project;
2. Location and size of the project implementation area;
3. Name and address of the project implementer and the name of its representative;
4. Reasons for changing the project implementer (applicable only where the project implementer is changed).
Article 5 (Applications for Approval of Implementation Plans)
(1) An application for approval or approval of an amendment to an implementation plan under Article 15(1) of the Act and the former part of Article 13(1) of the Decree shall be made using attached Form No. 4 or attached Form No. 5, respectively.
(2) "Documents prescribed by Ordinance of the Ministry of Land, Infrastructure and Transport" in the former part of Article 13(1) of the Decree means the following documents. Where an application is made for approval of an amendment to an implementation plan, only the amended matters shall be included:
1. A statement of project costs and a financing plan (including an investment plan for each year);
2. A plan view and design documents;
3. Details of the location, lot number, land category, area, ownership, and rights other than ownership of land, buildings, or objects affixed to land to be expropriated or used, rights other than ownership relating thereto, mining rights, fishery rights, aquaculture rights, and rights to use water (hereinafter referred to as "land and other property"), and the names and addresses of the owners and right holders;
4. Measures for the purchase of and compensation for land and other property, and for the relocation of residents;
5. A plan for the vesting without compensation and replacement of public facilities and land and other property;
6. A contract concerning the management and disposition of the land or facilities to be developed;
7. A contract for carrying out the special zone development project on behalf of the project implementer (applicable only where such an arrangement is planned);
8. Relevant documents and drawings necessary for decisions on urban or Gun management plans (including district unit plans);
9. Details of consultations concerning the implementation plan under Article 15(1) of the Act with Metropolitan City Mayors, Special Self-Governing City Mayors, Do Governors, and Special Self-Governing Province Governors of areas outside the Seoul Metropolitan Area under Article 2, subparagraph 1 of the Seoul Metropolitan Area Readjustment Planning Act, and with mayors of large cities with populations of at least 500,000, excluding Seoul Special Metropolitan City, Metropolitan Cities, and Special Self-Governing Cities, under Article 198(1) of the Local Autonomy Act. Such large cities include local governments deemed to be large cities with populations of at least 500,000 under the proviso to Article 58(1) of the Special Act on Local Autonomy, Decentralization, and Balanced Regional Development, excluding its subparagraphs, and are hereinafter referred to as "large cities"; the foregoing governors and mayors are hereinafter referred to as "Mayors/Do Governors, etc.";
10. Matters concerning permissions, authorizations, designations, approvals, consultations, reporting, and other procedures deemed completed under the subparagraphs of Article 17(1) of the Act.
Article 6 (Composition of Project Consultative Bodies)
(1) A project consultative body under Article 18(1) of the Act (hereinafter referred to as a "project consultative body") shall perform the following functions:
1. Providing opinions on matters concerning special zone development projects and urban convergence special zone linked projects (hereinafter referred to as "special zone linked projects") included in the master plan for the creation and fostering of an urban convergence special zone under Article 8(1) of the Act (hereinafter referred to as the "basic plan for an urban convergence special zone") and the implementation plan;
2. Consulting on coordination of construction schedules for special zone development projects and special zone linked projects, linkages between projects, and other relevant matters;
3. Other matters that Mayors/Do Governors, etc. consider necessary for the creation and fostering of an urban convergence special zone.
(2) A project consultative body shall have one chairperson and one vice chairperson.
(3) Where Mayors/Do Governors, etc. intend to commission a master planner under Article 18(2) of the Act, they shall first hear the opinions of the head of the Si, Gun, or Gu (meaning the head of an autonomous Gu).
(4) The term of office of a master planner shall be two years, and the master planner may be recommissioned for only one consecutive term.
(5) A master planner commissioned under Article 18(2) of the Act shall, if requested by Mayors/Do Governors, etc., provide opinions on a proposed basic plan for an urban convergence special zone or a proposed amendment thereto.
(6) Except as provided in paragraphs (1) through (5), details concerning the composition and operation of project consultative bodies and the commissioning and remuneration of master planners shall be prescribed by ordinance of the relevant Metropolitan City, Special Self-Governing City, Do, Special Self-Governing Province, or large city.
Article 7 (Applications for Authorization for Completion)
(1) An application for authorization for completion under Article 23(1) of the Act and Article 16(1) of the Decree shall be made using attached Form No. 6.
(2) Where the Minister of Land, Infrastructure and Transport grants authorization for completion under Article 23(4) of the Act, the Minister shall publicly announce the following matters in the Official Gazette or the official bulletin of the relevant local government, and issue a certificate of authorization for completion in attached Form No. 7 to the project implementer:
1. Name and address of the project implementer and the name of its representative;
2. Name of the special zone development project;
3. Location and area of the project implementation area;
4. Date of authorization for completion.
ADDENDA <Ordinance No. 1333, April 25, 2024>